Kingdom of Saudi Arabia
Riyadh Chamber of Commerce & Industry
General Directorate of Finance & Procurement — Contracts & Procurement Department
- Certificate no.
- 10
- Date
- 2026-08-22
- Hijri
- 9 Rabiʻ I 1448 AH
- Reference
- PAY-2025-012-10
Interim payment certificate no. (10)
For the work of August 2026
- Contract number
- RC/2025/012
- Supplier-portal reference
- 2503950550
- Contract
- Network & server equipment — disaster recovery site
- Contractor
- Smart Link Telecom & Security Systems Co.
- Contractor VAT number
- 340303165720003
- Project
- Disaster Recovery Centre for the Chamber’s Systems
- Contract period
- 2025-06-01 — 2026-11-30
- Original contract value
- 1,900,000
- Current contract value
- 1,900,000
- Linked milestone
- MEP systems installed · MS-G4 Testing & acceptance complete
Certificate summary (SAR)
| 1 | Total value of work completed to date | 1,172,000 |
| 2 | Less: previous certificates | (1,079,000) |
| 3 | Value of work in this certificate | 93,000 |
| 4 | Less: retention (5%) | (4,650) |
| 5 | Less: advance payment recovery (0%) | 0 |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (4,650) |
| 8 | Net before VAT | 88,350 |
| 9 | Add: value added tax (15%) | 13,253 |
| 10 | Net amount payable to the contractor | 101,603 |
Amount in words: One hundred one thousand six hundred three Saudi riyals only
Retention held up to this certificate: SAR 58.6K — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 133,000 | 125,200 | 7,800 | 133,000 | 100% |
| Earthworks & foundations | 342,000 | 320,100 | 21,900 | 342,000 | 100% |
| Concrete & structural works | 589,000 | 376,550 | 32,750 | 409,300 | 69% |
| Mechanical, electrical & plumbing | 456,000 | 176,900 | 20,000 | 196,900 | 43% |
| Finishes & external works | 285,000 | 70,000 | 9,100 | 79,100 | 28% |
| Testing & commissioning | 95,000 | 10,250 | 1,450 | 11,700 | 12% |
| Total | 1,900,000 | 1,079,000 | 93,000 | 1,172,000 | 62% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Ammar Y. Bakhashab
Supervising engineer
Eng. Ibrahim A. Al-Ghamdi
Project manager
Eng. Omar H. Bawazir
Finance & contracts
Khalid N. Al-Mutairi
Final approver
Dr. Abdullah S. Al-Qahtani