Kingdom of Saudi Arabia
Riyadh Chamber of Commerce & Industry
General Directorate of Finance & Procurement — Contracts & Procurement Department
- Certificate no.
- 11
- Date
- 2026-10-06
- Hijri
- 25 Rabiʻ II 1448 AH
- Reference
- PAY-2025-012-11
Interim payment certificate no. (11)
For the work of September 2026
- Contract number
- RC/2025/012
- Supplier-portal reference
- 2503950550
- Contract
- Network & server equipment — disaster recovery site
- Contractor
- Smart Link Telecom & Security Systems Co.
- Contractor VAT number
- 340303165720003
- Project
- Disaster Recovery Centre for the Chamber’s Systems
- Contract period
- 2025-06-01 — 2026-11-30
- Original contract value
- 1,900,000
- Current contract value
- 1,900,000
- Linked milestone
- MEP systems installed · MS-G4 Testing & acceptance complete
Certificate summary (SAR)
| 1 | Total value of work completed to date | 1,225,000 |
| 2 | Less: previous certificates | (1,172,000) |
| 3 | Value of work in this certificate | 53,000 |
| 4 | Less: retention (5%) | (2,650) |
| 5 | Less: advance payment recovery (0%) | 0 |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (2,650) |
| 8 | Net before VAT | 50,350 |
| 9 | Add: value added tax (15%) | 7,553 |
| 10 | Net amount payable to the contractor | 57,903 |
Amount in words: Fifty-seven thousand nine hundred three Saudi riyals only
Retention held up to this certificate: SAR 61.3K — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 133,000 | 128,900 | 4,100 | 133,000 | 100% |
| Earthworks & foundations | 342,000 | 330,350 | 11,650 | 342,000 | 100% |
| Concrete & structural works | 589,000 | 429,700 | 19,550 | 449,250 | 76% |
| Mechanical, electrical & plumbing | 456,000 | 194,250 | 11,550 | 205,800 | 45% |
| Finishes & external works | 285,000 | 77,400 | 5,300 | 82,700 | 29% |
| Testing & commissioning | 95,000 | 11,400 | 850 | 12,250 | 13% |
| Total | 1,900,000 | 1,172,000 | 53,000 | 1,225,000 | 64% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Ammar Y. Bakhashab
Supervising engineer
Eng. Ibrahim A. Al-Ghamdi
Project manager
Eng. Omar H. Bawazir
Finance & contracts
Khalid N. Al-Mutairi
Final approver
Dr. Abdullah S. Al-Qahtani