Kingdom of Saudi Arabia
Riyadh Chamber of Commerce & Industry
General Directorate of Finance & Procurement — Contracts & Procurement Department
- Certificate no.
- 6
- Date
- 2025-11-26
- Hijri
- 5 Jumada II 1447 AH
- Reference
- PAY-2025-013-06
Interim payment certificate no. (6)
For the work of November 2025
- Contract number
- RC/2025/013
- Supplier-portal reference
- 2504020563
- Contract
- QA & project office support — My Business Portal 2.0
- Contractor
- Dar Al-Mashura Management Consulting
- Contractor VAT number
- 310106912450003
- Project
- My Business Portal 2.0 — the Unified Member Journey
- Contract period
- 2025-03-02 — 2027-05-31
- Original contract value
- 270,000
- Current contract value
- 270,000
- Linked milestone
- Mid-term review · MS-05 Internal pilot (MVP) live
Certificate summary (SAR)
| 1 | Total value of work completed to date | 71,500 |
| 2 | Less: previous certificates | (56,500) |
| 3 | Value of work in this certificate | 15,000 |
| 4 | Less: retention (5%) | (750) |
| 5 | Less: advance payment recovery (0%) | 0 |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (750) |
| 8 | Net before VAT | 14,250 |
| 9 | Add: value added tax (15%) | 2,138 |
| 10 | Net amount payable to the contractor | 16,388 |
Amount in words: Sixteen thousand three hundred eighty-eight Saudi riyals only
Retention held up to this certificate: SAR 3,575 — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Resident engineering staff | 167,400 | 35,300 | 9,350 | 44,650 | 27% |
| Visiting specialists | 48,600 | 10,150 | 2,700 | 12,850 | 26% |
| Laboratory & testing | 32,400 | 6,050 | 1,650 | 7,700 | 24% |
| Reporting & technical office | 21,600 | 5,000 | 1,300 | 6,300 | 29% |
| Total | 270,000 | 56,500 | 15,000 | 71,500 | 26% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Salma R. Al-Buqami
Supervising engineer
Joud N. Al-Ahmadi
Project manager
Eng. Sultan F. Al-Ghamdi
Finance & contracts
Khalid N. Al-Mutairi
Final approver
Munirah A. Al-Khalidi