RC/2025/013
Terms, guarantees, milestones, variation orders and payment certificates.
From original to current value
The original value and each approved variation
60% of the current value paid
Paid
162Kof a current value of SAR 270K
Value of each certificate
The last 13 — gross and net
Approved: 13
Count: 13 · in the approval chain: 0
| Certificate | Submitted | Gross | Retention | Deductions | VAT | Net | Status | |
|---|---|---|---|---|---|---|---|---|
| Certificate 13September 2026 | 2026-10-06 | 6,000 | 300 | 0 | 855 | 6,555 | Approved | |
| Certificate 12August 2026 | 2026-08-22 | 9,000 | 450 | 0 | 1,283 | 9,833 | Approved | |
| Certificate 11June 2026 | 2026-07-08 | 10.5K | 525 | 0 | 1,496 | 11.5K | Approved | |
| Certificate 10May 2026 | 2026-05-25 | 15K | 750 | 0 | 2,138 | 16.4K | Approved | |
| Certificate 9March 2026 | 2026-04-10 | 15K | 750 | 0 | 2,138 | 16.4K | Approved | |
| Certificate 8February 2026 | 2026-02-24 | 16K | 800 | 0 | 2,280 | 17.5K | Approved | |
| Certificate 7December 2025 | 2026-01-10 | 19K | 950 | 0 | 2,708 | 20.8K | Approved | |
| Certificate 6November 2025 | 2025-11-26 | 15K | 750 | 0 | 2,138 | 16.4K | Approved | |
| Certificate 5September 2025 | 2025-10-12 | 16K | 800 | 0 | 2,280 | 17.5K | Approved | |
| Certificate 4August 2025 | 2025-08-29 | 14.5K | 725 | 0 | 2,066 | 15.8K | Approved | |
| Certificate 3June 2025 | 2025-07-15 | 10.5K | 525 | 0 | 1,496 | 11.5K | Approved | |
| Certificate 2May 2025 | 2025-05-31 | 9,500 | 475 | 0 | 1,354 | 10.4K | Approved | |
| Certificate 1March 2025 | 2025-04-16 | 6,000 | 300 | 0 | 855 | 6,555 | Approved |