Interim payment certificate no. (6)
For the work of April 2026
- Contract number
- RC/2025/020
- Supplier-portal reference
- 2504510654
- Contract
- Unified enterprise network roll-out — HQ & branches
- Contractor
- Smart Link Telecom & Security Systems Co.
- Contractor VAT number
- 340303165720003
- Project
- Unified Enterprise Network for HQ & the Branches
- Contract period
- 2025-06-01 — 2027-01-31
- Original contract value
- 5,400,000
- Current contract value
- 5,400,000
- Linked milestone
- MEP systems installed · MS-G4 Testing & acceptance complete
Certificate summary (SAR)
| 1 | Total value of work completed to date | 2,216,000 |
| 2 | Less: previous certificates | (1,846,000) |
| 3 | Value of work in this certificate | 370,000 |
| 4 | Less: retention (10%) | (37,000) |
| 5 | Less: advance payment recovery (10%) | (37,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (74,000) |
| 8 | Net before VAT | 296,000 |
| 9 | Add: value added tax (15%) | 44,400 |
| 10 | Net amount payable to the contractor | 340,400 |
Amount in words: Three hundred forty thousand four hundred Saudi riyals only
Retention held up to this certificate: SAR 221.6K — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 378,000 | 306,250 | 51,600 | 357,850 | 95% |
| Earthworks & foundations | 972,000 | 474,600 | 83,850 | 558,450 | 57% |
| Concrete & structural works | 1,674,000 | 628,550 | 127,100 | 755,650 | 45% |
| Mechanical, electrical & plumbing | 1,296,000 | 300,750 | 71,550 | 372,300 | 29% |
| Finishes & external works | 810,000 | 118,600 | 31,000 | 149,600 | 18% |
| Testing & commissioning | 270,000 | 17,250 | 4,900 | 22,150 | 8% |
| Total | 5,400,000 | 1,846,000 | 370,000 | 2,216,000 | 41% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Ammar Y. Bakhashab
Supervising engineer
Eng. Ibrahim A. Al-Ghamdi
Project manager
Eng. Omar H. Bawazir
Finance & contracts
Khalid N. Al-Mutairi
Final approver
Dr. Abdullah S. Al-Qahtani