Kingdom of Saudi Arabia
Riyadh Chamber of Commerce & Industry
General Directorate of Finance & Procurement — Contracts & Procurement Department
- Certificate no.
- 8
- Date
- 2026-09-05
- Hijri
- 23 Rabiʻ I 1448 AH
- Reference
- PAY-2025-020-08
Interim payment certificate no. (8)
For the work of August 2026
- Contract number
- RC/2025/020
- Supplier-portal reference
- 2504510654
- Contract
- Unified enterprise network roll-out — HQ & branches
- Contractor
- Smart Link Telecom & Security Systems Co.
- Contractor VAT number
- 340303165720003
- Project
- Unified Enterprise Network for HQ & the Branches
- Contract period
- 2025-06-01 — 2027-01-31
- Original contract value
- 5,400,000
- Current contract value
- 5,400,000
- Linked milestone
- MEP systems installed · MS-G4 Testing & acceptance complete
Certificate summary (SAR)
| 1 | Total value of work completed to date | 2,740,000 |
| 2 | Less: previous certificates | (2,555,500) |
| 3 | Value of work in this certificate | 184,500 |
| 4 | Less: retention (10%) | (18,450) |
| 5 | Less: advance payment recovery (10%) | (18,450) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (36,900) |
| 8 | Net before VAT | 147,600 |
| 9 | Add: value added tax (15%) | 22,140 |
| 10 | Net amount payable to the contractor | 169,740 |
Amount in words: One hundred sixty-nine thousand seven hundred forty Saudi riyals only
Retention held up to this certificate: SAR 274K — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 378,000 | 357,350 | 20,650 | 378,000 | 100% |
| Earthworks & foundations | 972,000 | 711,200 | 43,800 | 755,000 | 78% |
| Concrete & structural works | 1,674,000 | 870,900 | 63,450 | 934,350 | 56% |
| Mechanical, electrical & plumbing | 1,296,000 | 422,950 | 37,350 | 460,300 | 36% |
| Finishes & external works | 810,000 | 168,400 | 16,550 | 184,950 | 23% |
| Testing & commissioning | 270,000 | 24,700 | 2,700 | 27,400 | 10% |
| Total | 5,400,000 | 2,555,500 | 184,500 | 2,740,000 | 51% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Ammar Y. Bakhashab
Supervising engineer
Eng. Ibrahim A. Al-Ghamdi
Project manager
Eng. Omar H. Bawazir
Finance & contracts
Khalid N. Al-Mutairi
Final approver
Dr. Abdullah S. Al-Qahtani