Kingdom of Saudi Arabia
Riyadh Chamber of Commerce & Industry
General Directorate of Finance & Procurement — Contracts & Procurement Department
- Certificate no.
- 6
- Date
- 2026-08-18
- Hijri
- 5 Rabiʻ I 1448 AH
- Reference
- PAY-2025-024-06
Interim payment certificate no. (6)
For the work of July 2026
- Contract number
- RC/2025/024
- Supplier-portal reference
- 2504790706
- Contract
- Shaqra branch — rehabilitation works
- Contractor
- Northern Build Contracting Co.
- Contractor VAT number
- 333500279140003
- Project
- Shaqra Branch Rehabilitation
- Contract period
- 2025-11-02 — 2027-09-30
- Original contract value
- 1,650,000
- Current contract value
- 1,650,000
- Linked milestone
- Structure complete · MS-G3 Build complete
Certificate summary (SAR)
| 1 | Total value of work completed to date | 525,500 |
| 2 | Less: previous certificates | (451,500) |
| 3 | Value of work in this certificate | 74,000 |
| 4 | Less: retention (10%) | (7,400) |
| 5 | Less: advance payment recovery (10%) | (7,400) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (14,800) |
| 8 | Net before VAT | 59,200 |
| 9 | Add: value added tax (15%) | 8,880 |
| 10 | Net amount payable to the contractor | 68,080 |
Amount in words: Sixty-eight thousand eighty Saudi riyals only
Retention held up to this certificate: SAR 52.6K — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 115,500 | 74,050 | 10,800 | 84,850 | 73% |
| Earthworks & foundations | 297,000 | 115,150 | 17,300 | 132,450 | 45% |
| Concrete & structural works | 511,500 | 153,850 | 25,350 | 179,200 | 35% |
| Mechanical, electrical & plumbing | 396,000 | 74,550 | 13,750 | 88,300 | 22% |
| Finishes & external works | 247,500 | 29,600 | 5,850 | 35,450 | 14% |
| Testing & commissioning | 82,500 | 4,300 | 950 | 5,250 | 6% |
| Total | 1,650,000 | 451,500 | 74,000 | 525,500 | 32% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Badr N. Al-Shammari
Supervising engineer
Eng. Ibrahim A. Al-Ghamdi
Project manager
Eng. Mishari K. Al-Otaibi
Finance & contracts
Khalid N. Al-Mutairi
Final approver
Dr. Abdullah S. Al-Qahtani