Planned to date 67%
- SPI
- 0.87
- Forecast finish
- 2027-05-12
- Budget
- SAR 4.3M
42 days lateMaterial risks: 2Open impediments: 7Corrective plan CP-2026-01
Technical workshop with the vendor to close the Nafath & Government Service Bus integration.
Starts in
3 h 10 min2026-10-2817 Jumada I 1448 AH · 13:00
110 of 120 min
Nafath authentication sequence
DiscussionEng. Asma S. Al-Hamdan
40 min
Scenarios for pulling a business’s commercial-register data and collecting fees through SADAD
DiscussionHussam T. Al-Qurashi
40 min
Joint test plan
DecisionEng. Saad M. Al-Dosari
30 min
What will be presented and what needs a decision — read before the meeting
Nafath authentication sequence
DiscussionPresented by Eng. Asma S. Al-Hamdan40 min
Scenarios for pulling a business’s commercial-register data and collecting fees through SADAD
DiscussionPresented by Hussam T. Al-Qurashi40 min
Joint test plan
DecisionPresented by Eng. Saad M. Al-Dosari30 min
Needs a committee decision
From this committee’s earlier meetings and decisions — reviewed at the start
ACT-0301 · Eng. Sultan F. Al-Ghamdi
ACT-0306 · Eng. Sultan F. Al-Ghamdi
Project meeting — no quorum required
1 file
Drafted by the assistant from the agenda, the minutes, the decisions and the tasks. Review it before approval.
The summary is available once the meeting has been held and minuted.
Built automatically from the projects on the agenda: a card per project, the decisions needed, the support requested and the overdue tasks.
Planned to date 67%
42 days lateMaterial risks: 2Open impediments: 7Corrective plan CP-2026-01
Agenda item needing a decision
Joint test plan
From item 3
Change request awaiting decision · CR-2026-004
Add membership transfer & record merge to the first releaseMy Business Portal 2.0 — the Unified Member Journey
Corrective plan awaiting approval · CP-2026-01
My Business Portal 2.0 — the Unified Member JourneyISS-0103 · My Business Portal 2.0 — the Unified Member Journey
PeopleSAR 49K· Asked from: Change Committee
Three extra vendor integration engineers for four months through change request CR-2026-012
ISS-0101 · My Business Portal 2.0 — the Unified Member Journey
Coordination· Asked from: Dr. Abdullah S. Al-Qahtani
A letter from the Secretary-General to the National Information Center for a dedicated test environment for three months
CP-2026-01 · My Business Portal 2.0 — the Unified Member Journey
PeopleSAR 49K· Asked from: Change Committee
Approve change request CR-2026-012 for three integration engineers
Nothing