PRJ-2026-001 · From item 2
Chamber ERP on Dynamics 365Planned to date 74%
- SPI
- 0.82
- Forecast finish
- 2027-02-27
- Budget
- SAR 3.2M
58 days lateMaterial risks: 1Open impediments: 2Corrective plan CP-2026-05
November gates and the chamber ERP re-baseline.
Scheduled for
11:002026-11-0424 Jumada I 1448 AH · 11:00
85 of 90 min
Approve the previous minutes
ApprovalDr. Noura M. Al-Otaibi
5 min
Chamber ERP re-baseline
DecisionDana S. Al-Saleh
30 min
Acceptance & handover readiness — Business Centre (Exit 6) branch
DecisionEng. Waleed O. Al-Juhani
30 min
October data-quality scorecard
For informationTariq S. Al-Yami
20 min
What will be presented and what needs a decision — read before the meeting
Approve the previous minutes
ApprovalPresented by Dr. Noura M. Al-Otaibi5 min
Chamber ERP re-baseline
DecisionPresented by Dana S. Al-Saleh30 minPRJ-2026-001
Needs a committee decision
Acceptance & handover readiness — Business Centre (Exit 6) branch
DecisionPresented by Eng. Waleed O. Al-Juhani30 minPRJ-2026-036
Needs a committee decision
October data-quality scorecard
For informationPresented by Tariq S. Al-Yami20 min
From this committee’s earlier meetings and decisions — reviewed at the start
ACT-0315 · Dana S. Al-Saleh
ACT-0322 · Dr. Noura M. Al-Otaibi
Quorum: Four of eight members, including the chair or vice-chair
At least 4 voting members needed
0 files
Drafted by the assistant from the agenda, the minutes, the decisions and the tasks. Review it before approval.
The summary is available once the meeting has been held and minuted.
Built automatically from the projects on the agenda: a card per project, the decisions needed, the support requested and the overdue tasks.
PRJ-2026-001 · From item 2
Chamber ERP on Dynamics 365Planned to date 74%
58 days lateMaterial risks: 1Open impediments: 2Corrective plan CP-2026-05
PRJ-2026-036 · From item 3
Business Centre (Exit 6) Branch RehabilitationPlanned to date 99%
12 days late
Agenda item needing a decision · PRJ-2026-001
Chamber ERP re-baselineFrom item 2
Agenda item needing a decision · PRJ-2026-036
Acceptance & handover readiness — Business Centre (Exit 6) branchFrom item 3
Change request awaiting decision · CR-2026-008
Increase the customisation & integration budgetChamber ERP on Dynamics 365
CP-2026-05 · Chamber ERP on Dynamics 365
FundingSAR 340K· Asked from: Executive Committee
More customisation & integration budget through change request CR-2026-008
Nothing