Chamber ERP on Dynamics 365
Remove from watchlistOne system on Dynamics 365 for the chamber’s finance, procurement and HR, connected to the My Business portal to collect membership and service fees.
Budget (BAC)
Actual cost
69% of budget
Progress
Estimate at completion
SAR +440K
SPI · CPI
Forecast finish
58 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure4 November 2026
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionConditional goDate13 November 2024Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionConditional goDate12 January 2025Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionGoDate7 May 2025Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate4 November 2026Closure · Not startedClosure · Not started
Project lifecycle and its gates
Current phase: Execution. Pick a gate on the track to review it.
- Gate into «Initiation»DecisionConditional goDate13 November 2024Mandatory criteria met, with points to close during the next phase.Pre-startComplete
- Gate into «Planning»DecisionConditional goDate12 January 2025Mandatory criteria met, with points to close during the next phase.InitiationComplete
- Gate into «Execution»DecisionGoDate7 May 2025All criteria and required documents met.PlanningComplete
- Gate into «Closure»DecisionNot held yetDate4 November 2026ExecutionCurrent stageCurrent stage
- 5ClosureNot started
What each stage requires
The documents and approvals each gate asks for before the next stage.
Closure gate — deliverables accepted and handed over
Gate readiness
Enough for a conditional go only
Automated control: no move until the criteria are met
- 2 mandatory checklist items open
- 1 required document not approved
- 1 mandatory criterion under 70 points
- Weighted score 73 under the pass mark 75
Checklist
4 of 7 done
- Deliverable completion certificates approved for every deliverableMandatory
- Acceptance tests and handover to operations completeMandatory
- Open commitments listed with a plan to close themMandatory
- Deliverable-linked payments settledMandatory
- Pilot run with no critical or high findingsMandatory
- Users trained
- Launch rollback plan
Required documents
3 of 4 approved
- Deliverable completion certificatesApproved · V1
- Project closure & handover formNot submitted
- Lessons-learned logApproved · V1
- Benefits measurement planApproved · V1
Criteria and score
Go from 75, conditional from 60; a mandatory criterion is met from 70.
Deliverables acceptedweight 35%Not met
Awaiting evidence from the project team.
Quality & securityweight 25%Met
Awaiting evidence from the project team.
Operations & handover readinessweight 25%Met
Awaiting evidence from the project team.
User & training readinessweight 15%
Awaiting evidence from the project team.
Approvers
Project Management Office
- Dr. Noura M. Al-OtaibiPMO directorVote pending
- Munirah A. Al-KhalidiProject ownerVote pending
- Sarah A. Al-QarniProject sponsorVote pending