PRJ-2026-001Off track4ExecutionHybridStalled
Chamber ERP on Dynamics 365
Remove from watchlistOne system on Dynamics 365 for the chamber’s finance, procurement and HR, connected to the My Business portal to collect membership and service fees.
Project managerDana S. Al-SalehProject sponsorSarah A. Al-QarniProgrammeEnterprise Systems & Dynamics 365 Programme
Early warning: 86% chance of slipping within 30 days
Budget (BAC)
SAR 3.2M
Actual cost
SAR 2.2M
69% of budget
Progress
61%Awaiting acceptance 11%
Estimate at completion
SAR 3.7M
SAR +440K
SPI · CPI
0.82Schedule performance index · 0.820.88Cost performance index · 0.88
Forecast finish
2027-02-27
58 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure4 November 2026
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionConditional goDate13 November 2024Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionConditional goDate12 January 2025Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionGoDate7 May 2025Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate4 November 2026Closure · Not startedClosure · Not started
Periodic update cards
Filled by the project manager every period — progress, status, risks and support requested — prefilled from the previous card and the live data, then approved.
Period
October 2026
In approvalDue todayAction time limit about to lapse · Limit 2 working days
- Progress
- 61%
- Planned
- 74%
- SPI
- 0.82
Periodic update cards
| Period | Status | Progress | Current step | Date |
|---|---|---|---|---|
| October 2026UPD-001-2026-10 | In approval | 61% | Methodology reviewDr. Noura M. Al-OtaibiDue todayAction time limit about to lapse · Limit 2 working days | 2026-10-26 |
| September 2026UPD-001-2026-09 | Approved | 58% | — | 2026-10-02 |
| August 2026UPD-001-2026-08 | Approved | 54% | — | 2026-09-02 |