Riyadh ChamberMunjaz11My actionsNotifications
PRJ-2026-001Off track4ExecutionHybridStalled

Chamber ERP on Dynamics 365

Remove from watchlist

One system on Dynamics 365 for the chamber’s finance, procurement and HR, connected to the My Business portal to collect membership and service fees.

Early warning: ⁦86%⁩ chance of slipping within ⁦30⁩ days

Budget (BAC)

SAR 3.2M

Actual cost

SAR 2.2M

⁦69%⁩ of budget

Progress

⁦61%⁩Awaiting acceptance ⁦11%⁩

Estimate at completion

SAR 3.7M

SAR +440K

SPI · CPI

0.82Schedule performance index · 0.820.88Cost performance index · 0.88

Forecast finish

⁦2027-02-27⁩

58 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure4 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate13 November 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionConditional goDate12 January 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate7 May 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate4 November 2026Closure · Not startedClosure · Not started

Scope statementRequired at this stage

What the project delivers, what it does not, and when a deliverable counts as accepted.

⁦One system on Dynamics 365 for the chamber⁩’s finance, procurement and HR, connected to the My Business portal to collect membership and service fees.

In scope

  • ⁦One system on Dynamics 365 for the chamber⁩’s finance, procurement and HR, connected to the My Business portal to collect membership and service fees.
  • Migration from legacy systems
  • ERP integration

Out of scope

  • Operation and maintenance after the warranty period
  • Work outside the approved site or system boundary

Acceptance criteria

  • Main deliverable — stage 1Meets the approved specification, signed off by the project owner
  • Main deliverable — final stageMeets the approved specification, signed off by the project owner

Scope baselineRequired at this stage

Every approved change creates a new baseline

  1. 1

    SB-1Current⁦2025-02-16⁩

    Baseline approved at the planning gate

    Budget3.2MFinish⁦2026-12-31⁩

Requirements registerRequired at this stage

⁦6⁩ requirements of five kinds, with the trace status of each

By type

  • Business1
  • Functional1
  • Technical2
  • Regulatory1
  • Security1

Fully traced

⁦100%⁩

6/6 · linked to a deliverable, task and test

Test passed

⁦33%⁩

2/6 · test result is a pass

Accepted

⁦33%⁩

2/6 · signed off by the business owner

⁦6⁩ results
Export CSV
REQ-001-01One system for the proceduresBusinessMustIn progressMunirah A. Al-KhalidiMunirah A. Al-KhalidiDirector General, Finance & ProcurementP-018m.alkhalidi@chamber.saSB-1
REQ-001-02Historical data migrationTechnicalMustApprovedDana S. Al-SalehDana S. Al-SalehDirector, Enterprise Systems & IntegrationP-025d.alsaleh@chamber.saSB-1
REQ-001-03Ready operational reportsFunctionalMustIn progressMunirah A. Al-KhalidiMunirah A. Al-KhalidiDirector General, Finance & ProcurementP-018m.alkhalidi@chamber.saSB-1
REQ-001-04ERP integrationTechnicalShouldIn progressDana S. Al-SalehDana S. Al-SalehDirector, Enterprise Systems & IntegrationP-025d.alsaleh@chamber.saSB-1
REQ-001-05Data classificationRegulatoryCouldIn progressMunirah A. Al-KhalidiMunirah A. Al-KhalidiDirector General, Finance & ProcurementP-018m.alkhalidi@chamber.saSB-1
REQ-001-06Identity and access managementSecurityCouldApprovedDana S. Al-SalehDana S. Al-SalehDirector, Enterprise Systems & IntegrationP-025d.alsaleh@chamber.saSB-1
⁦1⁩–⁦6⁩ of ⁦6⁩

Traceability matrixRequired at this stage

Requirement → deliverable → task → test → acceptance. No requirement has a gap.