Riyadh ChamberMunjaz11My actionsNotifications
PRJ-2026-001Off track4ExecutionHybridStalled

Chamber ERP on Dynamics 365

Remove from watchlist

One system on Dynamics 365 for the chamber’s finance, procurement and HR, connected to the My Business portal to collect membership and service fees.

Early warning: ⁦86%⁩ chance of slipping within ⁦30⁩ days

Budget (BAC)

SAR 3.2M

Actual cost

SAR 2.2M

⁦69%⁩ of budget

Progress

⁦61%⁩Awaiting acceptance ⁦11%⁩

Estimate at completion

SAR 3.7M

SAR +440K

SPI · CPI

0.82Schedule performance index · 0.820.88Cost performance index · 0.88

Forecast finish

⁦2027-02-27⁩

58 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure4 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate13 November 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionConditional goDate12 January 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate7 May 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate4 November 2026Closure · Not startedClosure · Not started

Project management plan

One plan bringing the schedule, deliverables, risks, communications, quality and benefits together from the project’s records, approved through the plan’s chain.

Riyadh ChamberMunjazStrategy & projectsMunjazPMO PLATFORM

Planning

Project management plan

Schedule, deliverables, risks, communications, quality and benefits

Form no.
RC-PMO-F05
Template edition
2.0
Version
V2
Form date
⁦2025-02-06⁩
Hijri
7 Shaʻban 1446 AH
ApprovedPRJ-2026-001Chamber ERP on Dynamics 365

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-001
Project
Chamber ERP on Dynamics 365
Portfolio
Technology & Enterprise Systems Portfolio
Sector
Digital Transformation & IT
Sponsor
Sarah A. Al-Qarni
Project manager
Dana S. Al-Saleh

1ScheduleAuto-filled

From the project schedule and its approved baseline.

Start

⁦2025-01-12⁩

Baseline finish

⁦2026-12-31⁩

Forecast finish

⁦2027-02-27⁩

SPI

0.82

MilestonePlannedForecastSlip
Project plan approved⁦2025-06-22⁩⁦2025-09-26⁩+96 days
Designs approved⁦2025-10-24⁩⁦2026-04-12⁩+170 days
Build complete⁦2026-04-27⁩⁦2026-11-27⁩+214 days
Testing & acceptance complete⁦2026-08-29⁩⁦2027-01-12⁩+136 days
Final handover⁦2026-12-31⁩⁦2027-02-27⁩+58 days

2DeliverablesAuto-filled

DeliverableWeightDueOwner
Project plan & baseline⁦5%⁩⁦2025-04-21⁩Dana S. Al-Saleh
Monitoring & reporting⁦4%⁩⁦2025-06-22⁩Munirah A. Al-Khalidi
Business requirements⁦10%⁩⁦2025-08-23⁩Munirah A. Al-Khalidi
Solution design⁦10%⁩⁦2025-10-24⁩Sarah A. Al-Qarni
Release 1⁦16%⁩⁦2025-12-25⁩Sarah A. Al-Qarni
Release 2⁦16%⁩⁦2026-02-25⁩Dana S. Al-Saleh
Integrations⁦11%⁩⁦2026-04-27⁩Munirah A. Al-Khalidi
System testing⁦8%⁩⁦2026-06-28⁩Dana S. Al-Saleh
User acceptance testing⁦8%⁩⁦2026-08-29⁩Munirah A. Al-Khalidi
Training & change⁦6%⁩⁦2026-10-30⁩Munirah A. Al-Khalidi
Go-live & handover⁦6%⁩⁦2026-12-31⁩Sarah A. Al-Qarni
Accepted with a certificate⁦61%⁩——

3RisksAuto-filled

CodeRiskScoreResponseOwner
RSK-0012Customisation and My Business portal integration costs exceeding the approved contingency16EscalateDana S. Al-Saleh
RSK-0013Late migration and reconciliation of historical financial data12MitigateDana S. Al-Saleh
RSK-0014Implementation consultants’ contracts ending before go-live9MitigateMunirah A. Al-Khalidi

4CommunicationsAuto-filled

AudienceNeedFrequencyOwner
Project sponsorStatus and decisions neededMonthlyDana S. Al-Saleh
Project ownerDeliverable status and acceptance datesFortnightlyDana S. Al-Saleh
PMOData and indicator updatesWeeklyDana S. Al-Saleh
BeneficiariesWhat changes and whenAt each milestoneDana S. Al-Saleh
Team memberRoleAllocation
Dana S. Al-SalehProject manager⁦60%⁩
Eng. Asma S. Al-HamdanChamber ERP solution architecture⁦40%⁩
Haifa S. Al-RuwailiFinancial analyst⁦10%⁩
—Finance & procurement functional lead⁦100%⁩

5QualityAuto-filled

  • Peer review of every deliverable before acceptance
  • Written acceptance criteria for every deliverable
  • A PMO audit at every gate

6BenefitsAuto-filled

BenefitBaselineTargetOwner
No benefits recorded

Approval logChain: Project management plan approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Dana S. Al-SalehDirector, Enterprise Systems & IntegrationSubmitted—⁦2025-02-06⁩ 11:56
2Methodology review — PMOMethodology reviewGhada A. Al-ShahraniPMO — analystApprovedComplete against the project management plan template.⁦2025-02-10⁩ 13:28
3Technical acceptance — project ownerTechnical acceptanceMunirah A. Al-KhalidiProject ownerApproved—⁦2025-02-13⁩ 14:35
4Cash flow & financial commitmentFinancial approvalMunirah A. Al-KhalidiFinanceApproved—⁦2025-02-17⁩ 12:51
5Plan aligned with the contractsFinancial approvalMazen A. Al-HazmiProcurement & contractsApproved—⁦2025-02-18⁩ 13:28
6Sponsor approvalTechnical acceptanceSarah A. Al-QarniProject sponsorApproved—⁦2025-02-23⁩ 11:56

Signatures

Methodology review — PMO

Ghada A. Al-Shahrani

Approved⁦2025-02-10⁩

Technical acceptance — project owner

Munirah A. Al-Khalidi

Approved⁦2025-02-13⁩

Cash flow & financial commitment

Munirah A. Al-Khalidi

Approved⁦2025-02-17⁩

Plan aligned with the contracts

Mazen A. Al-Hazmi

Approved⁦2025-02-18⁩

Sponsor approval

Sarah A. Al-Qarni

Approved⁦2025-02-23⁩

Issued from Munjaz — Riyadh Chamber · ⁦2026-10-28⁩Form RC-PMO-F05 · version V2

Project management plan

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Project management plan approval · version ⁦1⁩

Submitted by Dana S. Al-Saleh on ⁦2025-02-06⁩

  1. Methodology review

    Methodology review — PMO

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2025-02-10⁩ at ⁦13:28⁩

    Complete against the project management plan template.

  2. Technical acceptance

    Technical acceptance — project owner

    Munirah A. Al-Khalidi · Project owner

    Approved · ⁦2025-02-13⁩ at ⁦14:35⁩

  3. Financial approval

    Cash flow & financial commitment

    Munirah A. Al-Khalidi · Finance

    On the path because: Financial link?

    Approved · ⁦2025-02-17⁩ at ⁦12:51⁩

  4. Financial approval

    Plan aligned with the contracts

    Mazen A. Al-Hazmi · Procurement & contracts

    On the path because: Contract link?

    Approved · ⁦2025-02-18⁩ at ⁦13:28⁩

  5. Technical acceptance

    Sponsor approval

    Sarah A. Al-Qarni · Project sponsor

    Approved · ⁦2025-02-23⁩ at ⁦11:56⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V2ApprovedCurrent⁦2025-02-06⁩

    Approved with the baseline

    • Schedule and cost baseline approved

    Dana S. Al-Saleh

  2. V1Returned for edit⁦2025-01-23⁩

    First draft — returned to complete the quality plan

    • Plan from the methodology template

    Dana S. Al-Saleh

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close