PRJ-2026-007
Training & Employment Centre ComplexPlanned to date 82%
- SPI
- 0.70
- Forecast finish
- 2027-06-01
- Budget
- SAR 32M
152 days lateMaterial risks: 3Open impediments: 4Corrective plan CP-2026-03
First dispute-board meeting on the training complex contractor claims.
Scheduled for
10:002026-11-1030 Jumada I 1448 AH · 10:00
180 of 180 min
Contractor presents its claims
DiscussionEng. Shahad M. Al-Malki
60 min
The chamber’s response and the independent engineer
DiscussionEng. Abdulrahman S. Al-Harbi
60 min
Deliberation and next steps
DecisionEng. Turki A. Al-Anazi
60 min
What will be presented and what needs a decision — read before the meeting
Contractor presents its claims
DiscussionPresented by Eng. Shahad M. Al-Malki60 min
The chamber’s response and the independent engineer
DiscussionPresented by Eng. Abdulrahman S. Al-Harbi60 min
Deliberation and next steps
DecisionPresented by Eng. Turki A. Al-Anazi60 min
Needs a committee decision
From this committee’s earlier meetings and decisions — reviewed at the start
ACT-0310 · Eng. Shahad M. Al-Malki
ACT-0312 · Eng. Abdulrahman S. Al-Harbi
Project meeting — no quorum required
1 file
Drafted by the assistant from the agenda, the minutes, the decisions and the tasks. Review it before approval.
The summary is available once the meeting has been held and minuted.
Built automatically from the projects on the agenda: a card per project, the decisions needed, the support requested and the overdue tasks.
PRJ-2026-007
Training & Employment Centre ComplexPlanned to date 82%
152 days lateMaterial risks: 3Open impediments: 4Corrective plan CP-2026-03
Agenda item needing a decision
Deliberation and next steps
From item 3
Change request awaiting decision · CR-2026-005
Variation 7: revise the central HVAC systemTraining & Employment Centre Complex
Change request awaiting decision · CR-2026-006
Extend the contract by 150 daysTraining & Employment Centre Complex
Corrective plan awaiting approval · CP-2026-03
Training & Employment Centre ComplexISS-0109 · Training & Employment Centre Complex
A decision· Asked from: Executive Committee
A decision to accept an equivalent façade alternative on the consultant’s advice, or to extend the supply period
CP-2026-03 · Training & Employment Centre Complex
A decision· Asked from: Executive Committee
A decision to accept an equivalent façade on the consultant’s advice
ACT-0311 · Eng. Ibrahim A. Al-Ghamdi