Riyadh ChamberMunjaz11My actionsNotifications
PRJ-2026-009At risk4ExecutionHybridIn progress

Moving the Chamber’s Systems & Website to the Cloud

Add to watchlist

Moving 46 systems to a licensed in-Kingdom cloud and the website from SharePoint to a modern content platform.

Budget (BAC)

SAR 2.6M

Actual cost

SAR 1.3M

⁦48%⁩ of budget

Progress

⁦47%⁩Awaiting acceptance ⁦12%⁩

Estimate at completion

SAR 2.7M

SAR +80K

SPI · CPI

0.89Schedule performance index · 0.890.97Cost performance index · 0.97

Forecast finish

⁦2027-03-21⁩

21 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure8 January 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate2 April 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionConditional goDate1 June 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate11 September 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate8 January 2027Closure · Not startedClosure · Not started

Project lifecycle and its gates

Current phase: Execution. Pick a gate on the track to review it.

  1. Gate into «Initiation»DecisionGoDate2 April 2025All criteria and required documents met.Pre-startComplete
  2. Gate into «Planning»DecisionConditional goDate1 June 2025Mandatory criteria met, with points to close during the next phase.InitiationComplete
  3. Gate into «Execution»DecisionGoDate11 September 2025All criteria and required documents met.PlanningComplete
  4. Gate into «Closure»DecisionNot held yetDate8 January 2027ExecutionCurrent stageCurrent stage
  5. 5ClosureNot started

What each stage requires

The documents and approvals each gate asks for before the next stage.

G4Next gateProject Management Office

Closure gate — deliverables accepted and handed over

4Execution5ClosurePlanned for ⁦2027-01-08⁩In 72 days2027-01-0830 Rajab 1448 AH
68/100

Gate readiness

Enough for a conditional go only

Automated control: no move until the criteria are met

  • ⁦3⁩ mandatory checklist items open
  • ⁦2⁩ required documents not approved
  • ⁦1⁩ mandatory criterion under ⁦70⁩ points
  • Weighted score ⁦68⁩ under the pass mark ⁦75⁩

Checklist

⁦4⁩ of ⁦7⁩ done

  • Deliverable completion certificates approved for every deliverableMandatory
  • Acceptance tests and handover to operations completeMandatory
  • Open commitments listed with a plan to close themMandatory
  • Deliverable-linked payments settledMandatory
  • Pilot run with no critical or high findingsMandatory
  • Users trained
  • Launch rollback plan

Required documents

⁦2⁩ of ⁦4⁩ approved

  • Deliverable completion certificatesNot submitted
  • Project closure & handover formApproved · V1
  • Lessons-learned logApproved · V1
  • Benefits measurement planNot submitted

Criteria and score

Go from ⁦75⁩, conditional from ⁦60⁩; a mandatory criterion is met from ⁦70⁩.

  • Deliverables acceptedweight ⁦35⁩%Not met

    Awaiting evidence from the project team.

  • Quality & securityweight ⁦25⁩%Met

    Awaiting evidence from the project team.

  • Operations & handover readinessweight ⁦25⁩%Met

    Awaiting evidence from the project team.

  • User & training readinessweight ⁦15⁩%

    Awaiting evidence from the project team.

Approvers

Project Management Office

  • Dr. Noura M. Al-OtaibiPMO directorVote pending
  • Eng. Nayef H. Al-BuqamiProject ownerVote pending
  • Eng. Majed S. Al-RasheedProject sponsorVote pending

Gate decision

The decision and its rationale go into the gate log and to the team.

What is the decision based on? It stays in the log.0 / 600

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close