PRJ-2026-009At risk4ExecutionHybridIn progress

Moving the Chamber’s Systems & Website to the Cloud

Add to watchlist

Moving 46 systems to a licensed in-Kingdom cloud and the website from SharePoint to a modern content platform.

Budget (BAC)

SAR 2.6M

Actual cost

SAR 1.3M

⁦48%⁩ of budget

Progress

⁦47%⁩Awaiting acceptance ⁦12%⁩

Estimate at completion

SAR 2.7M

SAR +80K

SPI · CPI

0.89Schedule performance index · 0.890.97Cost performance index · 0.97

Forecast finish

⁦2027-03-21⁩

21 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure8 January 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate2 April 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionConditional goDate1 June 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate11 September 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate8 January 2027Closure · Not startedClosure · Not started

Finance & earned value

The full budget structure, cost broken down by eight dimensions, cash flow with its S-curve, and earned-value indicators with an automatic end-of-project forecast.

Budget anatomy

The approved SAR 2.6M split into spent, committed and left, with the estimate at completion

Forecast overrun SAR 80K
EAC SAR 2.7M
Revised request SAR 2.6M
  • Actual spendSAR 1.3M
  • Committed, not spentSAR 790K
  • Allotted, uncommittedSAR 472K
  • Contingency availableSAR 78K

Budget

EstimatedManualFrom the project proposal — not from the finance systemthe proposal’s cost before approval
SAR 2.5M
Original budgetwhen the first baseline was approved
SAR 2.6M
Approved budgetafter approved change requests
SAR 2.6M
Current budgetavailable to spend now
SAR 2.6M
Revised budgetif the pending changes are approved
SAR 2.6M

Commitments

CommitmentsSyncedFrom the nightly finance-system syncsigned contracts and purchase orders
SAR 2.1M
Contracts1 active contract
SAR 1.9M
Purchase orders⁦2⁩ orders
SAR 150K
Remaining budgetapproved less actual
SAR 1.3M

Spend & outlook

Actual costSyncedFrom the nightly finance-system syncincluding accruals
SAR 1.3M
Accrualswork done, not yet invoiced
SAR 50K
Estimate at completionManualThe project manager’s estimate — not from the finance systemthe PM’s bottom-up forecast
SAR 2.7M
ContingencySAR 52K drawn of SAR 130K
SAR 78K

Estimated vs approved budget

What the project proposal estimated before approval, against today’s approved budget and the estimate at completion

EstimatedSAR 2.5M
ApprovedSAR 2.6M
Estimate at completionSAR 2.7M
Approved is SAR 105K (⁦4.2%⁩) above the estimate
The estimate at completion is SAR 185K (⁦7.4%⁩) above the estimate

From the «project proposal & feasibility study» approved at the approval gate on ⁦2025-03-18⁩ · The gap between estimated and approved comes from the scope update and the change requests approved after the approval gate.

ERP link — data readiness

The link keys are ready for the finance-system sync; Munjaz follows the project and does not replace the accounting system

⁦4⁩ of ⁦4⁩ fields ready
  • Cost centreCC-61009
  • WBS elements⁦5⁩ elements · P-2026-009.01 …
  • Purchase orders⁦2⁩ synced · ⁦0⁩ manual
  • Invoices & certificates⁦6⁩ posted · ⁦0⁩ in approval
Last sync⁦2026-10-28⁩ · 06:00 · succeededNext tonight at 02:00

Where each figure comes from

  • EstimatedManualFrom the project proposal — not from the finance system
  • CommitmentsSyncedFrom the nightly finance-system sync
  • Actual costSyncedFrom the nightly finance-system sync
  • Estimate at completionManualThe project manager’s estimate — not from the finance system

Once the link is live, synced figures are read from the finance system; manual updates stay available to the same roles and are logged.

Purchase-order register

Manual edit log

Every manual update — who, when, why and from which source

No manual edits on this project

All its figures come from the finance-system sync. Finance & procurement — and the project manager, for the estimate at completion — can update them by hand.

Budget bridge

From the original to the revised request

  • Total
  • Increase
  • Decrease

Contingency draw-downs

SAR 52K drawn of SAR 130K

  • Covering realised delivery risks⁦2026-08-29⁩SAR 52K

Purchase orders

Cost breakdown structure

Every dimension adds up to the same totals

Cost breakdown structure — WBS
ItemBudgetSAR MCommittedSAR MActualSAR MEACSAR MVarianceSAR MConsumption
1Management & governance0.200.210.210.21⁦−0.01⁩
2Analysis & design0.430.460.460.46⁦−0.03⁩
3Build1.010.840.591.03⁦−0.03⁩
4Testing & acceptance0.500.310.000.54⁦−0.03⁩
5Launch & handover0.380.230.000.40⁦−0.02⁩
Unallocated contingency0.080.000.000.04⁦+0.04⁩
Total2.602.051.262.68⁦−0.08⁩

Budget split

WBS

SAR 2.6M

Budget

  • Management & governanceSAR 201.8K⁦8%⁩
  • Analysis & designSAR 428.7K⁦16%⁩
  • BuildSAR 1M⁦39%⁩
  • Testing & acceptanceSAR 504.4K⁦19%⁩
  • Launch & handoverSAR 378.3K⁦15%⁩
  • Unallocated contingencySAR 78K⁦3%⁩

Cash flow

Planned, committed, actual and forecast

Spend per period

SAR millions

  • Planned
  • Actual
  • Forecast

Cumulative S-curve

Cumulative to close

  • Actual, then forecast
  • Planned, cumulative
  • Committed, cumulative
  • Forecast

Earned value management

At the data date ⁦2026-10-28⁩

Planned value, earned value and actual cost

  • Planned value
  • Earned value
  • Actual cost
  • Estimate at completion
  • Budget at completion

Finish by earned schedule

⁦2028-05-10⁩+437

SPI(t) ⁦0.59⁩ against the approved finish ⁦2027-02-28⁩

Planned valuePV
SAR 2.4M
The value of the work that should be done by today.
PV
Earned valueEV
SAR 1.2M
The value of the work actually done, at plan prices.
EV = % complete × BAC
Actual costAC
SAR 1.3M
What has actually been spent on the work done.
AC
Budget at completionBAC
SAR 2.6M
The approved budget for the whole project.
BAC
Cost varianceCV
⁦−0.04⁩ SAR M
Earned less actual; negative means paying more than the value.
CV = EV − AC
Schedule varianceSV
⁦−1.13⁩ SAR M
Earned less planned; negative means behind, in value.
SV = EV − PV
Cost performance indexCPI
0.97
Value produced per riyal spent; under 1 is an overrun.
CPI = EV ÷ AC
Schedule performance indexSPI
0.52
Work done over work planned; under 1 is behind.
SPI = EV ÷ PV
Estimate at completionEAC
SAR 2.7M
What the project will cost when it finishes, as forecast.
EAC = BAC ÷ CPI
Estimate to completeETC
SAR 1.4M
What is still to be spent to completion.
ETC = EAC − AC
Variance at completionVAC
⁦−0.08⁩ SAR M
Budget less the estimate; negative is an overrun.
VAC = BAC − EAC
To-complete performance indexTCPI
1.03
The cost efficiency the rest must reach to stay on budget.
TCPI = (BAC − EV) ÷ (BAC − AC)

Automatic end-of-project forecast

Four ways to estimate the final cost, and the date earned schedule points to

  • At today’s cost performanceSAR 2.7M
  • If the rest goes to planSAR 2.6M
  • At cost and schedule performanceSAR 4M
  • The PM’s bottom-up estimateSAR 2.7M
  • To stay within SAR 2.6M, cost performance on the rest must rise to ⁦1.03⁩ — above what has been achieved.

Estimate at completion at that performance

SAR 2.7M

Variance at completion: ⁦−0.08⁩ SAR M