PRJ-2026-009At risk4ExecutionHybridIn progress

Moving the Chamber’s Systems & Website to the Cloud

Add to watchlist

Moving 46 systems to a licensed in-Kingdom cloud and the website from SharePoint to a modern content platform.

Budget (BAC)

SAR 2.6M

Actual cost

SAR 1.3M

⁦48%⁩ of budget

Progress

⁦47%⁩Awaiting acceptance ⁦12%⁩

Estimate at completion

SAR 2.7M

SAR +80K

SPI · CPI

0.89Schedule performance index · 0.890.97Cost performance index · 0.97

Forecast finish

⁦2027-03-21⁩

21 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure8 January 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate2 April 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionConditional goDate1 June 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate11 September 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate8 January 2027Closure · Not startedClosure · Not started

Work breakdown structure

The project’s scope broken down from phase to subtask, with codes, owners, durations, dates, progress, cost, links and deliverables. Drag any element to re-order it among its siblings; the codes renumber.

Structure levels

Pick a level to open the tree to that depth

Allotted to work2.5M⁦16⁩ elements
Unallocated contingency78KSAR 130K
Budget at completion2.6MPRJ-2026-009
Weighted progress⁦47%⁩Linked deliverables: 0
ElementLevelOwnerDurationStart – finishProgressBudgetSAR MActualSAR MLinksDeliverables
Project655⁦2025-06-01⁩⁦2027-03-18⁩⁦47%⁩2.521.26—
1
Phase238⁦2025-06-01⁩⁦2026-01-25⁩⁦100%⁩0.200.21—
1.1
WBS element147⁦2025-06-01⁩⁦2025-10-26⁩⁦100%⁩0.100.110 / 1
1.2
WBS element146⁦2025-09-01⁩⁦2026-01-25⁩⁦100%⁩0.100.111 / 2
2
Phase239⁦2025-12-01⁩⁦2026-07-28⁩⁦100%⁩0.430.46—
2.1
WBS element147⁦2025-12-01⁩⁦2026-04-27⁩⁦100%⁩0.210.231 / 1
2.2
WBS element147⁦2026-03-03⁩⁦2026-07-28⁩⁦100%⁩0.210.231 / 2
3
Phase292⁦2026-03-03⁩⁦2026-12-20⁩⁦55%⁩1.010.59—
3.1
WBS element146⁦2026-06-03⁩⁦2026-10-27⁩⁦100%⁩0.340.361 / 1
3.2
WBS element270⁦2026-03-03⁩⁦2026-11-28⁩⁦65%⁩0.340.231 / 1
3.3
WBS element36⁦2026-11-14⁩⁦2026-12-20⁩⁦0%⁩0.34—1 / 2
4
Phase58⁦2026-12-06⁩⁦2027-02-02⁩⁦0%⁩0.50——
4.1
WBS element36⁦2026-12-06⁩⁦2027-01-11⁩⁦0%⁩0.25—1 / 1
4.2
WBS element36⁦2026-12-28⁩⁦2027-02-02⁩⁦0%⁩0.25—1 / 2
5
Phase58⁦2027-01-19⁩⁦2027-03-18⁩⁦0%⁩0.38——
5.1
WBS element36⁦2027-01-19⁩⁦2027-02-24⁩⁦0%⁩0.19—1 / 1
5.2
WBS element36⁦2027-02-10⁩⁦2027-03-18⁩⁦0%⁩0.19—1 / 1
Total⁦47%⁩2.521.26