Riyadh ChamberMunjaz11My actionsNotifications
PRJ-2026-009At risk4ExecutionHybridIn progress

Moving the Chamber’s Systems & Website to the Cloud

Add to watchlist

Moving 46 systems to a licensed in-Kingdom cloud and the website from SharePoint to a modern content platform.

Budget (BAC)

SAR 2.6M

Actual cost

SAR 1.3M

⁦48%⁩ of budget

Progress

⁦47%⁩Awaiting acceptance ⁦12%⁩

Estimate at completion

SAR 2.7M

SAR +80K

SPI · CPI

0.89Schedule performance index · 0.890.97Cost performance index · 0.97

Forecast finish

⁦2027-03-21⁩

21 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure8 January 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate2 April 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionConditional goDate1 June 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate11 September 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate8 January 2027Closure · Not startedClosure · Not started

Schedule & Gantt

The plan with its planned, actual and forecast dates, baselines, links and critical path. The forecast is scheduled from the data date through the links and constraints.

Finish-date drift

⁦+18⁩ days vs approved

Baseline (original = approved)⁦2027-02-28⁩
Current forecast⁦2027-03-18⁩
By earned schedule⁦2028-05-10⁩
Critical activities
7
of ⁦9⁩ open activities
Late activities
6
past their baseline finish
Schedule performance
0.52
earned ÷ planned value
Next milestone
in 53 days
Build complete
Expand allCollapse all
Activity
Moving the Chamber’s Systems & Website to the CloudPlanned: ⁦2025-06-01⁩ → ⁦2027-02-28⁩Forecast: ⁦2025-06-01⁩ → ⁦2027-03-18⁩Float: ⁦0⁩d
Management & governancePlanned: ⁦2025-06-01⁩ → ⁦2025-10-22⁩Actual: ⁦2025-06-01⁩ → ⁦2026-01-25⁩
Project plan & baselinePlanned: ⁦2025-06-01⁩ → ⁦2025-08-28⁩Actual: ⁦2025-06-01⁩ → ⁦2025-10-26⁩
Monitoring & reportingPlanned: ⁦2025-07-26⁩ → ⁦2025-10-22⁩Actual: ⁦2025-09-01⁩ → ⁦2026-01-25⁩
Project plan approvedPlanned: ⁦2025-10-22⁩ → ⁦2025-10-22⁩Actual: ⁦2026-01-25⁩ → ⁦2026-01-25⁩Project plan approved
Analysis & designPlanned: ⁦2025-09-19⁩ → ⁦2026-02-09⁩Actual: ⁦2025-12-01⁩ → ⁦2026-07-28⁩
Business requirementsPlanned: ⁦2025-09-19⁩ → ⁦2025-12-16⁩Actual: ⁦2025-12-01⁩ → ⁦2026-04-27⁩
Solution designPlanned: ⁦2025-11-13⁩ → ⁦2026-02-09⁩Actual: ⁦2026-03-03⁩ → ⁦2026-07-28⁩
Designs approvedPlanned: ⁦2026-02-09⁩ → ⁦2026-02-09⁩Actual: ⁦2026-07-28⁩ → ⁦2026-07-28⁩Designs approved
BuildPlanned: ⁦2026-01-07⁩ → ⁦2026-07-23⁩Forecast: ⁦2026-03-03⁩ → ⁦2026-12-20⁩Float: ⁦0⁩d
Release 1Planned: ⁦2026-01-07⁩ → ⁦2026-04-05⁩Actual: ⁦2026-06-03⁩ → ⁦2026-10-27⁩
Release 2Planned: ⁦2026-03-03⁩ → ⁦2026-05-29⁩Forecast: ⁦2026-03-03⁩ → ⁦2026-11-28⁩Float: ⁦0⁩dDrag to change its duration+183
IntegrationsPlanned: ⁦2026-04-26⁩ → ⁦2026-07-23⁩Forecast: ⁦2026-11-14⁩ → ⁦2026-12-20⁩Float: ⁦0⁩dDrag to change its dates+150
Build completePlanned: ⁦2026-07-23⁩ → ⁦2026-07-23⁩Forecast: ⁦2026-12-20⁩ → ⁦2026-12-20⁩Float: ⁦88⁩dDrag to change its datesBuild complete
Testing & acceptancePlanned: ⁦2026-06-20⁩ → ⁦2026-11-10⁩Forecast: ⁦2026-12-06⁩ → ⁦2027-02-02⁩Float: ⁦0⁩d
System testingPlanned: ⁦2026-06-20⁩ → ⁦2026-09-16⁩Forecast: ⁦2026-12-06⁩ → ⁦2027-01-11⁩Float: ⁦0⁩dDrag to change its dates+117
User acceptance testingPlanned: ⁦2026-08-14⁩ → ⁦2026-11-10⁩Forecast: ⁦2026-12-28⁩ → ⁦2027-02-02⁩Float: ⁦0⁩dDrag to change its dates+84
Testing & acceptance completePlanned: ⁦2026-11-10⁩ → ⁦2026-11-10⁩Forecast: ⁦2027-02-02⁩ → ⁦2027-02-02⁩Float: ⁦44⁩dDrag to change its datesTesting & acceptance complete
Launch & handoverPlanned: ⁦2026-10-08⁩ → ⁦2027-02-28⁩Forecast: ⁦2027-01-19⁩ → ⁦2027-03-18⁩Float: ⁦0⁩d
Training & changePlanned: ⁦2026-10-08⁩ → ⁦2027-01-04⁩Forecast: ⁦2027-01-19⁩ → ⁦2027-02-24⁩Float: ⁦0⁩dDrag to change its dates+51
Go-live & handoverPlanned: ⁦2026-12-02⁩ → ⁦2027-02-28⁩Forecast: ⁦2027-02-10⁩ → ⁦2027-03-18⁩Float: ⁦0⁩dDrag to change its dates+18
Final handoverPlanned: ⁦2027-02-28⁩ → ⁦2027-02-28⁩Forecast: ⁦2027-03-18⁩ → ⁦2027-03-18⁩Float: ⁦0⁩dDrag to change its datesFinal handover
  • Activities (forecast)
  • Baseline
  • Slip past baseline
  • Critical
  • Milestone
  • Phase / element
  • Today

⁦22⁩ rows shown · Data date ⁦2026-10-28⁩

AI schedule analysis

Computed from the current plan: ⁦9⁩ open activities, data date ⁦2026-10-28⁩

Critical-path risk⁦95%⁩ confidence

The critical path runs through ⁦6⁩ activities with no float

Every day lost on this chain is a day lost at launch. No other activity has three weeks of float or less.
Unrealistic durations⁦78%⁩ confidence

“Release 2” needs a pace ⁦4.2⁩× faster than it has kept

It earned ⁦65%⁩ in 239 days; the forecast assumes the rest in 31 days. At the pace so far it finishes on ⁦2027-03-06⁩.

Slippage pattern⁦84%⁩ confidence

Milestones slip 125 days on average

Each milestone’s slip in days, in date order; the later ones slip more than the early ones.

95
169
150
84
G1G2G3G4

The critical chain

In date order, to final acceptance

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close