PRJ-2026-010On track4ExecutionConstructionIn progress
Solar Power for the Chamber’s Buildings & Branches
Add to watchlist6 MW of rooftop and carport solar on 14 buildings and branches, the largest array at the training centre complex.
Project managerEng. Mishari K. Al-OtaibiProject sponsorSarah A. Al-QarniProgrammeBuilding Rehabilitation & Efficiency Programme
Budget (BAC)
SAR 4.8M
Actual cost
SAR 2.8M
57% of budget
Progress
58%Awaiting acceptance 10%
Estimate at completion
SAR 4.8M
SPI · CPI
1.02Schedule performance index · 1.021.01Cost performance index · 1.01
Forecast finish
2027-04-22
On baseline
ExecutionStage 4 of 5
Next gate:Closure26 February 2027
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate1 January 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionConditional goDate2 March 2025Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionGoDate6 July 2025Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate26 February 2027Closure · Not startedClosure · Not started