PRJ-2026-010On track4ExecutionConstructionIn progress

Solar Power for the Chamber’s Buildings & Branches

Add to watchlist

6 MW of rooftop and carport solar on 14 buildings and branches, the largest array at the training centre complex.

Budget (BAC)

SAR 4.8M

Actual cost

SAR 2.8M

⁦57%⁩ of budget

Progress

⁦58%⁩Awaiting acceptance ⁦10%⁩

Estimate at completion

SAR 4.8M

SPI · CPI

1.02Schedule performance index · 1.021.01Cost performance index · 1.01

Forecast finish

⁦2027-04-22⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure26 February 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate1 January 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionConditional goDate2 March 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate6 July 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate26 February 2027Closure · Not startedClosure · Not started

Project charter

Objective, scope, deliverables, roles and budget

Riyadh ChamberMunjazStrategy & projectsMunjazPMO PLATFORM

Initiation

Project charter

Objective, scope, deliverables, roles and budget

Form no.
RC-PMO-F04
Template edition
3.0
Version
V2
Form date
⁦2025-02-28⁩
Hijri
29 Shaʻban 1446 AH
ApprovedPRJ-2026-010Solar Power for the Chamber’s Buildings & Branches

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-010
Project
Solar Power for the Chamber’s Buildings & Branches
Portfolio
Building Rehabilitation & Sustainability Portfolio
Sector
Support Services Sector
Sponsor
Sarah A. Al-Qarni
Project manager
Eng. Mishari K. Al-Otaibi

1Objective

Background

6 MW of rooftop and carport solar on 14 buildings and branches, the largest array at the training centre complex.

Project objectives

  1. Financial sustainability
  2. The chamber’s services across Riyadh city and its governorates

2Scope

In scope

  • 6 MW of rooftop and carport solar on 14 buildings and branches, the largest array at the training centre complex.
  • Saudi Building Code compliance
  • An approved plan to keep member services and training running during the works

Out of scope

  • Operation and maintenance after the warranty period
  • Work outside the approved site or system boundary

3Deliverables and milestones

DeliverableDue
Project management plan⁦2025-04-02⁩
Main deliverable — stage 1⁦2026-04-09⁩
Main deliverable — final stage⁦2027-01-10⁩
Final report⁦2027-04-30⁩
MilestoneDate
Charter approved⁦2025-02-28⁩
Contract signed⁦2025-07-06⁩
50% of works complete⁦2026-04-09⁩
Provisional acceptance⁦2027-02-26⁩
Closure⁦2027-04-30⁩

4RolesAuto-filled

SponsorAuto-filled
Sarah A. Al-Qarni
Project ownerAuto-filled
Eng. Bandar M. Al-Shammari
Project managerAuto-filled
Eng. Mishari K. Al-Otaibi
StakeholderRole
Project sponsorDecisions and funding
Project ownerAccepts deliverables, owns benefits
Project Management Office (PMO)Governance and compliance
Governance bodyRoleCadence
Change CommitteeApproves scope, cost and schedule changesWeekly
PMO CommitteeMethodology compliance, data quality, stage gatesFortnightly
Project management teamDay-to-day control, risks, impediments, the periodic update cardWeekly

5BudgetAuto-filled

LineAmount
Main contractSAR 3.5M
Supervision & consultingSAR 675K
Internal teamSAR 430K
Contingency reserve (5%)SAR 240K
Approved budgetSAR 4.8M

Funding

The owning sector’s approved budget

6Success criteria and constraints

Success criteria

  • Delivered within the approved budget
  • On the approved date ±5%
  • Target benefits within 12 months

Constraints

  • Stay within the approved budget
  • Comply with the Government Tenders & Procurement Law

Assumptions

  • Named internal staff available throughout
  • Approvals land within the workflow’s action time limits

Approval logChain: Project charter approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Eng. Mishari K. Al-OtaibiDirector, Sustainability & Social ResponsibilitySubmitted—⁦2025-02-19⁩ 10:00
2PMO complianceMethodology reviewDr. Noura M. Al-OtaibiPMO — directorApproved—⁦2025-02-22⁩ 12:30
3Project ownerTechnical acceptanceEng. Bandar M. Al-ShammariProject ownerApproved—⁦2025-02-25⁩ 09:45
4Budget funding confirmedFinancial approvalMunirah A. Al-KhalidiFinanceApproved—⁦2025-02-26⁩ 11:10
5Sponsor approvalTechnical acceptanceSarah A. Al-QarniProject sponsorApproved—⁦2025-02-28⁩ 11:00

Signatures

PMO compliance

Dr. Noura M. Al-Otaibi

Approved⁦2025-02-22⁩

Project owner

Eng. Bandar M. Al-Shammari

Approved⁦2025-02-25⁩

Budget funding confirmed

Munirah A. Al-Khalidi

Approved⁦2025-02-26⁩

Sponsor approval

Sarah A. Al-Qarni

Approved⁦2025-02-28⁩

Issued from Munjaz — Riyadh Chamber · ⁦2026-10-28⁩Form RC-PMO-F04 · version V2

Project charter

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Project charter approval · version ⁦1⁩

Submitted by Eng. Mishari K. Al-Otaibi on ⁦2025-02-19⁩

  1. Methodology review

    PMO compliance

    Dr. Noura M. Al-Otaibi · PMO — director

    Approved · ⁦2025-02-22⁩ at ⁦12:30⁩

  2. Technical acceptance

    Project owner

    Eng. Bandar M. Al-Shammari · Project owner

    Approved · ⁦2025-02-25⁩ at ⁦09:45⁩

  3. Financial approval

    Budget funding confirmed

    Munirah A. Al-Khalidi · Finance

    On the path because: Financial link?

    Approved · ⁦2025-02-26⁩ at ⁦11:10⁩

  4. Technical acceptance

    Sponsor approval

    Sarah A. Al-Qarni · Project sponsor

    Approved · ⁦2025-02-28⁩ at ⁦11:00⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V2ApprovedCurrent⁦2025-02-28⁩

    Approved version

    • PMO comments addressed

    Eng. Mishari K. Al-Otaibi

  2. V1Returned for edit⁦2025-02-09⁩

    First draft

    • Returned to detail the budget

    Eng. Mishari K. Al-Otaibi

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close