Solar Power for the Chamber’s Buildings & Branches
Add to watchlist6 MW of rooftop and carport solar on 14 buildings and branches, the largest array at the training centre complex.
Budget (BAC)
Actual cost
57% of budget
Progress
Estimate at completion
SPI · CPI
Forecast finish
On baseline
ExecutionStage 4 of 5
Next gate:Closure26 February 2027
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate1 January 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionConditional goDate2 March 2025Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionGoDate6 July 2025Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate26 February 2027Closure · Not startedClosure · Not started
Milestones
Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.
Milestone runway
The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay
Milestone register
Display options
| Project plan approvedMS-G1 | Executive | 2025-08-12 | 2025-09-25 | +44 days | Eng. Mishari K. Al-OtaibiEng. Mishari K. Al-OtaibiDirector, Sustainability & Social ResponsibilityP-028m.alotaibi@chamber.sa | Achieved | 1 | Approved |
| Designs approvedMS-G2 | Project | 2025-12-15 | 2026-03-03 | +78 days | Eng. Mishari K. Al-OtaibiEng. Mishari K. Al-OtaibiDirector, Sustainability & Social ResponsibilityP-028m.alotaibi@chamber.sa | Achieved | 1 | Approved |
| Build completeMS-G3 | Contractual | 2026-06-21 | 2026-10-26 | +127 days | Eng. Mishari K. Al-OtaibiEng. Mishari K. Al-OtaibiDirector, Sustainability & Social ResponsibilityP-028m.alotaibi@chamber.sa | Achieved | 1 | Approved |
| Testing & acceptance completeMS-G4 | Regulatory | 2026-12-26 | 2027-03-05 | +69 days | Eng. Mishari K. Al-OtaibiEng. Mishari K. Al-OtaibiDirector, Sustainability & Social ResponsibilityP-028m.alotaibi@chamber.sa | At risk | 0 | Not requested |
| Final handoverMS-G5 | Payment | 2027-04-30 | 2027-04-30 | On time | Eng. Mishari K. Al-OtaibiEng. Mishari K. Al-OtaibiDirector, Sustainability & Social ResponsibilityP-028m.alotaibi@chamber.sa | On track | 0 | Not requested |
Deliverables register
Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.
Progress counted from deliverables
Project progress = the sum of the weights of deliverables accepted with a completion certificate. Nothing counts before it is accepted and certified.
Weights sum to 100%
Counted
58%Awaiting acceptance
10%Not handed in
32%Deliverable flow
Display options
| Project plan & baseline010-D1 | 3% | CRT-010-01 | Approved | Eng. Mishari K. Al-OtaibiEng. Mishari K. Al-OtaibiDirector, Sustainability & Social ResponsibilityP-028m.alotaibi@chamber.sa | Eng. Bandar M. Al-Shammari | 2025-06-10 | V1 | 3 of 3 |
| Monitoring & reporting010-D2 | 3% | CRT-010-02 | Approved | Eng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Facilities & General ServicesP-013b.alshammari@chamber.sa | Eng. Bandar M. Al-Shammari | 2025-08-12 | V1 | 3 of 3 |
| Detailed design010-D3 | 7% | CRT-010-03 | Approved | Eng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Facilities & General ServicesP-013b.alshammari@chamber.sa | Eng. Bandar M. Al-Shammari | 2025-10-13 | V1 | 3 of 3 |
| Permits & approvals010-D4 | 6% | CRT-010-04 | Approved | Sarah A. Al-QarniSarah A. Al-QarniAssistant Secretary-General, Support ServicesP-012s.alqarni@chamber.sa | Eng. Bandar M. Al-Shammari | 2025-12-15 | V1 | 3 of 3 |
| Site works & excavation010-D5 | 13% | CRT-010-05 | Approved | Sarah A. Al-QarniSarah A. Al-QarniAssistant Secretary-General, Support ServicesP-012s.alqarni@chamber.sa | Eng. Bandar M. Al-Shammari | 2026-02-16 | V1 | 3 of 3 |
| Structure010-D6 | 13% | CRT-010-06 | Approved | Eng. Mishari K. Al-OtaibiEng. Mishari K. Al-OtaibiDirector, Sustainability & Social ResponsibilityP-028m.alotaibi@chamber.sa | Eng. Bandar M. Al-Shammari | 2026-04-19 | V1 | 3 of 3 |
| Finishes010-D7 | 13% | CRT-010-07 | Approved | Eng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Facilities & General ServicesP-013b.alshammari@chamber.sa | Eng. Bandar M. Al-Shammari | 2026-06-21 | V1 | 3 of 3 |
| Supply010-D8 | 10% | — | Submitted | Eng. Mishari K. Al-OtaibiEng. Mishari K. Al-OtaibiDirector, Sustainability & Social ResponsibilityP-028m.alotaibi@chamber.sa | Eng. Bandar M. Al-Shammari | 2026-08-23 | V1 | 1 of 3 |
| Installation010-D9 | 9% | — | Draft | Eng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Facilities & General ServicesP-013b.alshammari@chamber.sa | Eng. Bandar M. Al-Shammari | 2026-10-24 | V0 | 0 of 3 |
| Testing & commissioning010-D10 | 9% | — | Draft | Sarah A. Al-QarniSarah A. Al-QarniAssistant Secretary-General, Support ServicesP-012s.alqarni@chamber.sa | Eng. Bandar M. Al-Shammari | 2026-12-26 | V0 | 0 of 3 |
| Provisional acceptance010-D11 | 7% | — | Draft | Eng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Facilities & General ServicesP-013b.alshammari@chamber.sa | Eng. Bandar M. Al-Shammari | 2027-02-26 | V0 | 0 of 3 |
| Final acceptance010-D12 | 7% | — | Draft | Sarah A. Al-QarniSarah A. Al-QarniAssistant Secretary-General, Support ServicesP-012s.alqarni@chamber.sa | Eng. Bandar M. Al-Shammari | 2027-04-30 | V0 | 0 of 3 |
| Total · 12 | 100% |