Riyadh ChamberMunjaz11My actionsNotifications
PRJ-2026-010On track4ExecutionConstructionIn progress

Solar Power for the Chamber’s Buildings & Branches

Add to watchlist

6 MW of rooftop and carport solar on 14 buildings and branches, the largest array at the training centre complex.

Budget (BAC)

SAR 4.8M

Actual cost

SAR 2.8M

⁦57%⁩ of budget

Progress

⁦58%⁩Awaiting acceptance ⁦10%⁩

Estimate at completion

SAR 4.8M

SPI · CPI

1.02Schedule performance index · 1.021.01Cost performance index · 1.01

Forecast finish

⁦2027-04-22⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure26 February 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate1 January 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionConditional goDate2 March 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate6 July 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate26 February 2027Closure · Not startedClosure · Not started

Schedule & Gantt

The plan with its planned, actual and forecast dates, baselines, links and critical path. The forecast is scheduled from the data date through the links and constraints.

Finish-date drift

⁦0⁩ days vs approved

Baseline (original = approved) · Current forecast⁦2027-04-30⁩
By earned schedule⁦2028-03-02⁩
Critical activities
1
of ⁦7⁩ open activities
Late activities
4
past their baseline finish
Schedule performance
0.67
earned ÷ planned value
Next milestone
in 128 days
Testing & acceptance complete
Expand allCollapse all
Activity
Solar Power for the Chamber’s Buildings & BranchesPlanned: ⁦2025-03-02⁩ → ⁦2027-04-30⁩Forecast: ⁦2025-03-02⁩ → ⁦2027-04-30⁩Float: ⁦0⁩d
Management & governancePlanned: ⁦2025-03-02⁩ → ⁦2025-08-12⁩Actual: ⁦2025-03-02⁩ → ⁦2025-09-25⁩
Project plan & baselinePlanned: ⁦2025-03-02⁩ → ⁦2025-06-10⁩Actual: ⁦2025-03-02⁩ → ⁦2025-07-07⁩
Monitoring & reportingPlanned: ⁦2025-05-04⁩ → ⁦2025-08-12⁩Actual: ⁦2025-05-21⁩ → ⁦2025-09-25⁩
Project plan approvedPlanned: ⁦2025-08-12⁩ → ⁦2025-08-12⁩Actual: ⁦2025-09-25⁩ → ⁦2025-09-25⁩Project plan approved
Design & permitsPlanned: ⁦2025-07-05⁩ → ⁦2025-12-15⁩Actual: ⁦2025-08-08⁩ → ⁦2026-03-03⁩
Detailed designPlanned: ⁦2025-07-05⁩ → ⁦2025-10-13⁩Actual: ⁦2025-08-08⁩ → ⁦2025-12-14⁩
Permits & approvalsPlanned: ⁦2025-09-06⁩ → ⁦2025-12-15⁩Actual: ⁦2025-10-27⁩ → ⁦2026-03-03⁩
Designs approvedPlanned: ⁦2025-12-15⁩ → ⁦2025-12-15⁩Actual: ⁦2026-03-03⁩ → ⁦2026-03-03⁩Designs approved
Civil worksPlanned: ⁦2025-11-07⁩ → ⁦2026-06-21⁩Actual: ⁦2026-01-14⁩ → ⁦2026-10-26⁩
Site works & excavationPlanned: ⁦2025-11-07⁩ → ⁦2026-02-16⁩Actual: ⁦2026-01-14⁩ → ⁦2026-05-22⁩
StructurePlanned: ⁦2026-01-09⁩ → ⁦2026-04-19⁩Actual: ⁦2026-04-04⁩ → ⁦2026-08-09⁩
FinishesPlanned: ⁦2026-03-13⁩ → ⁦2026-06-21⁩Actual: ⁦2026-06-23⁩ → ⁦2026-10-26⁩
Build completePlanned: ⁦2026-06-21⁩ → ⁦2026-06-21⁩Actual: ⁦2026-10-26⁩ → ⁦2026-10-26⁩Build complete
MEP worksPlanned: ⁦2026-05-14⁩ → ⁦2026-12-26⁩Forecast: ⁦2026-05-14⁩ → ⁦2027-03-05⁩Float: ⁦8⁩d
SupplyPlanned: ⁦2026-05-14⁩ → ⁦2026-08-23⁩Forecast: ⁦2026-05-14⁩ → ⁦2027-01-16⁩Float: ⁦8⁩dDrag to change its duration+146
InstallationPlanned: ⁦2026-07-16⁩ → ⁦2026-10-24⁩Forecast: ⁦2027-01-02⁩ → ⁦2027-02-09⁩Float: ⁦8⁩dDrag to change its dates+108
Testing & commissioningPlanned: ⁦2026-09-17⁩ → ⁦2026-12-26⁩Forecast: ⁦2027-01-26⁩ → ⁦2027-03-05⁩Float: ⁦8⁩dDrag to change its dates+69
Testing & acceptance completePlanned: ⁦2026-12-26⁩ → ⁦2026-12-26⁩Forecast: ⁦2027-03-05⁩ → ⁦2027-03-05⁩Float: ⁦56⁩dDrag to change its datesTesting & acceptance complete
HandoverPlanned: ⁦2026-11-18⁩ → ⁦2027-04-30⁩Forecast: ⁦2027-02-19⁩ → ⁦2027-04-30⁩Float: ⁦0⁩d
Provisional acceptancePlanned: ⁦2026-11-18⁩ → ⁦2027-02-26⁩Forecast: ⁦2027-02-19⁩ → ⁦2027-03-29⁩Float: ⁦8⁩dDrag to change its dates+31
Final acceptancePlanned: ⁦2027-01-20⁩ → ⁦2027-04-30⁩Forecast: ⁦2027-03-15⁩ → ⁦2027-04-22⁩Float: ⁦8⁩dDrag to change its dates
Final handoverPlanned: ⁦2027-04-30⁩ → ⁦2027-04-30⁩Forecast: ⁦2027-04-30⁩ → ⁦2027-04-30⁩Float: ⁦0⁩dDrag to change its datesFinal handover
  • Activities (forecast)
  • Baseline
  • Slip past baseline
  • Critical
  • Milestone
  • Phase / element
  • Today

⁦23⁩ rows shown · Data date ⁦2026-10-28⁩

AI schedule analysis

Computed from the current plan: ⁦7⁩ open activities, data date ⁦2026-10-28⁩

Critical-path risk⁦95%⁩ confidence

The critical path runs through ⁦0⁩ activities with no float

Every day lost on this chain is a day lost at launch. ⁦5⁩ more activities have three weeks of float or less.
Unrealistic durations⁦78%⁩ confidence

“Supply” needs a pace ⁦8.4⁩× faster than it has kept

It earned ⁦20%⁩ in 167 days; the forecast assumes the rest in 80 days. At the pace so far it finishes on ⁦2028-08-26⁩.

Slippage pattern⁦84%⁩ confidence

Milestones slip 80 days on average — and it is getting worse

Each milestone’s slip in days, in date order; the later ones slip more than the early ones.

44
78
127
69
G1G2G3G4

The critical chain

In date order, to final acceptance

Near-critical

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close