Riyadh ChamberMunjaz11My actionsNotifications
PRJ-2026-022On track3PlanningStage-GateNot started

Chamber Channel & Podcast Studio — with a Media Sponsor

Add to watchlist

A filming and broadcast studio for the chamber’s channel, its podcast and the digital Tijarat Al-Riyadh magazine, co-funded by a private-sector media sponsor.

Budget (BAC)

SAR 2.3M

Actual cost

SAR 46K

⁦2%⁩ of budget

Progress

⁦2%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SAR 2.3M

SPI · CPI

1.00Schedule performance index · 1.001.00Cost performance index · 1.00

Forecast finish

⁦2028-03-31⁩

On baseline

PlanningStage ⁦3⁩ of ⁦5⁩

Next gate:Execution7 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate3 June 2026Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate2 August 2026Planning · Current stagePlanning · Current stage
  4. Gate into «Execution»DecisionNot held yetDate7 November 2026Execution · Not startedExecution · Not started
  5. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started

Project lifecycle and its gates

Current phase: Planning. Pick a gate on the track to review it.

  1. Gate into «Initiation»DecisionGoDate3 June 2026All criteria and required documents met.Pre-startComplete
  2. Gate into «Planning»DecisionGoDate2 August 2026All criteria and required documents met.InitiationComplete
  3. Gate into «Execution»DecisionNot held yetDate7 November 2026PlanningCurrent stageCurrent stage
  4. Gate into «Closure»DecisionNot held yet4ExecutionNot started
  5. 5ClosureNot started

What each stage requires

The documents and approvals each gate asks for before the next stage.

G3Next gateStrategy & Projects Steering Committee

Planning gate — plan and baseline approved

3Planning4ExecutionPlanned for ⁦2026-11-07⁩In 10 days2026-11-0727 Jumada I 1448 AH
86/100

Gate readiness

Meets the pass mark

Automated control: no move until the criteria are met

  • ⁦2⁩ required documents not approved

Checklist

⁦6⁩ of ⁦6⁩ done

  • Project management plan: schedule, deliverables, risks, communication, quality and benefitsMandatory
  • ⁦Deliverables defined with weights that sum to 100%⁩Mandatory
  • Schedule and baseline approved and lockedMandatory
  • Approved budget and expected commitmentsMandatory
  • Finance and procurement sign-off where money or a contract is involvedMandatory
  • Initial risk register

Required documents

⁦2⁩ of ⁦4⁩ approved

  • Project management planNot submitted
  • Approved baselineApproved · V1
  • Deliverables register with weightsNot submitted
  • Contract or purchase orderApproved · V1

Criteria and score

Go from ⁦75⁩, conditional from ⁦60⁩; a mandatory criterion is met from ⁦70⁩.

  • Schedule realismweight ⁦30⁩%Met

    Awaiting evidence from the project team.

  • Cost estimate completenessweight ⁦30⁩%Met

    Awaiting evidence from the project team.

  • Deliverables and acceptance criteria clearweight ⁦25⁩%Met

    Awaiting evidence from the project team.

  • Quality of the risk planweight ⁦15⁩%

    Awaiting evidence from the project team.

Approvers

Strategy & Projects Steering Committee

  • Dr. Abdullah S. Al-QahtaniSteering Committee chairVote pending
  • Eng. Majed S. Al-RasheedProject sponsorVote pending
  • Dr. Noura M. Al-OtaibiPMO directorVote pending
  • Munirah A. Al-KhalidiFinance & procurementVote pending

Gate decision

The decision and its rationale go into the gate log and to the team.

What is the decision based on? It stays in the log.0 / 600

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close