Chamber Channel & Podcast Studio — with a Media Sponsor
Add to watchlistA filming and broadcast studio for the chamber’s channel, its podcast and the digital Tijarat Al-Riyadh magazine, co-funded by a private-sector media sponsor.
Budget (BAC)
Actual cost
2% of budget
Progress
Estimate at completion
SPI · CPI
Forecast finish
On baseline
PlanningStage 3 of 5
Next gate:Execution7 November 2026
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate3 June 2026Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate2 August 2026Planning · Current stagePlanning · Current stage
- Gate into «Execution»DecisionNot held yetDate7 November 2026Execution · Not startedExecution · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
Milestones
Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.
Milestone runway
The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay
Milestone register
Display options
| Project plan approvedMS-G1 | Executive | 2026-12-05 | 2027-01-08 | +34 days | Rami Al-KhatibRami Al-KhatibEvents & Riyadh Economic Forum ConsultantP-045r.alkhatib@chamber.sa | At risk | 0 | Not requested |
| Designs approvedMS-G2 | Project | 2027-03-12 | 2027-04-08 | +27 days | Rami Al-KhatibRami Al-KhatibEvents & Riyadh Economic Forum ConsultantP-045r.alkhatib@chamber.sa | At risk | 0 | Not requested |
| Build completeMS-G3 | Contractual | 2027-08-03 | 2027-08-21 | +18 days | Rami Al-KhatibRami Al-KhatibEvents & Riyadh Economic Forum ConsultantP-045r.alkhatib@chamber.sa | On track | 0 | Not requested |
| Testing & acceptance completeMS-G4 | Regulatory | 2027-12-26 | 2028-01-03 | +8 days | Rami Al-KhatibRami Al-KhatibEvents & Riyadh Economic Forum ConsultantP-045r.alkhatib@chamber.sa | On track | 0 | Not requested |
| Final handoverMS-G5 | Payment | 2028-03-31 | 2028-04-02 | +2 days | Rami Al-KhatibRami Al-KhatibEvents & Riyadh Economic Forum ConsultantP-045r.alkhatib@chamber.sa | On track | 0 | Not requested |
Deliverables register
Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.
Progress counted from deliverables
Project progress = the sum of the weights of deliverables accepted with a completion certificate. Nothing counts before it is accepted and certified.
Weights sum to 100%
Counted
2%Awaiting acceptance
0%Not handed in
98%Deliverable flow
Display options
| Project plan & baseline022-D1 | 2% | CRT-022-01 | Approved | Rami Al-KhatibRami Al-KhatibEvents & Riyadh Economic Forum ConsultantP-045r.alkhatib@chamber.sa | Nawaf S. Al-Ajmi | 2026-10-18 | V1 | 3 of 3 |
| Monitoring & reporting022-D2 | 3% | — | Draft | Nawaf S. Al-AjmiNawaf S. Al-AjmiExecutive Director, Corporate Communication & MarketingP-050n.alajmi@chamber.sa | Nawaf S. Al-Ajmi | 2026-12-05 | V0 | 0 of 3 |
| Detailed design022-D3 | 6% | — | Draft | Nawaf S. Al-AjmiNawaf S. Al-AjmiExecutive Director, Corporate Communication & MarketingP-050n.alajmi@chamber.sa | Nawaf S. Al-Ajmi | 2027-01-22 | V0 | 0 of 3 |
| Permits & approvals022-D4 | 6% | — | Draft | Eng. Majed S. Al-RasheedEng. Majed S. Al-RasheedExecutive Director, Digital Transformation & ITP-011m.alrasheed@chamber.sa | Nawaf S. Al-Ajmi | 2027-03-12 | V0 | 0 of 3 |
| Site works & excavation022-D5 | 13% | — | Draft | Eng. Majed S. Al-RasheedEng. Majed S. Al-RasheedExecutive Director, Digital Transformation & ITP-011m.alrasheed@chamber.sa | Nawaf S. Al-Ajmi | 2027-04-29 | V0 | 0 of 3 |
| Structure022-D6 | 13% | — | Draft | Rami Al-KhatibRami Al-KhatibEvents & Riyadh Economic Forum ConsultantP-045r.alkhatib@chamber.sa | Nawaf S. Al-Ajmi | 2027-06-16 | V0 | 0 of 3 |
| Finishes022-D7 | 13% | — | Draft | Nawaf S. Al-AjmiNawaf S. Al-AjmiExecutive Director, Corporate Communication & MarketingP-050n.alajmi@chamber.sa | Nawaf S. Al-Ajmi | 2027-08-03 | V0 | 0 of 3 |
| Supply022-D8 | 10% | — | Draft | Rami Al-KhatibRami Al-KhatibEvents & Riyadh Economic Forum ConsultantP-045r.alkhatib@chamber.sa | Nawaf S. Al-Ajmi | 2027-09-20 | V0 | 0 of 3 |
| Installation022-D9 | 10% | — | Draft | Nawaf S. Al-AjmiNawaf S. Al-AjmiExecutive Director, Corporate Communication & MarketingP-050n.alajmi@chamber.sa | Nawaf S. Al-Ajmi | 2027-11-07 | V0 | 0 of 3 |
| Testing & commissioning022-D10 | 10% | — | Draft | Eng. Majed S. Al-RasheedEng. Majed S. Al-RasheedExecutive Director, Digital Transformation & ITP-011m.alrasheed@chamber.sa | Nawaf S. Al-Ajmi | 2027-12-26 | V0 | 0 of 3 |
| Provisional acceptance022-D11 | 7% | — | Draft | Nawaf S. Al-AjmiNawaf S. Al-AjmiExecutive Director, Corporate Communication & MarketingP-050n.alajmi@chamber.sa | Nawaf S. Al-Ajmi | 2028-02-12 | V0 | 0 of 3 |
| Final acceptance022-D12 | 7% | — | Draft | Eng. Majed S. Al-RasheedEng. Majed S. Al-RasheedExecutive Director, Digital Transformation & ITP-011m.alrasheed@chamber.sa | Nawaf S. Al-Ajmi | 2028-03-31 | V0 | 0 of 3 |
| Total · 12 | 100% |