Kingdom of Saudi Arabia
Riyadh Chamber of Commerce & Industry
General Directorate of Finance & Procurement — Contracts & Procurement Department
- Certificate no.
- 6
- Date
- 2024-08-09
- Hijri
- 5 Safar 1446 AH
- Reference
- PAY-2024-003-06
Interim payment certificate no. (6)
For the work of July 2024
- Contract number
- RC/2024/003
- Supplier-portal reference
- 2401220043
- Contract
- Design & build — current HQ rehabilitation & committee-room wing
- Contractor
- United Buildings & Operations Co.
- Contractor VAT number
- 320510488360003
- Project
- Converting the Current Headquarters into a Member Services Centre & Committee Rooms
- Contract period
- 2024-02-01 — 2026-09-30
- Original contract value
- 17,600,000
- Current contract value
- 18,670,000including variations of SAR 1.1M
- Linked milestone
- Earthworks & foundations complete · MS-G2 Designs approved
Certificate summary (SAR)
| 1 | Total value of work completed to date | 1,673,500 |
| 2 | Less: previous certificates | (1,318,000) |
| 3 | Value of work in this certificate | 355,500 |
| 4 | Less: retention (10%) | (35,550) |
| 5 | Less: advance payment recovery (10%) | (35,550) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (71,100) |
| 8 | Net before VAT | 284,400 |
| 9 | Add: value added tax (15%) | 42,660 |
| 10 | Net amount payable to the contractor | 327,060 |
Amount in words: Three hundred twenty-seven thousand sixty Saudi riyals only
Retention held up to this certificate: SAR 167.4K — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 1,306,900 | 214,200 | 56,100 | 270,300 | 21% |
| Earthworks & foundations | 3,360,600 | 333,600 | 88,100 | 421,700 | 13% |
| Concrete & structural works | 5,787,700 | 449,300 | 121,350 | 570,650 | 10% |
| Mechanical, electrical & plumbing | 4,480,800 | 219,950 | 61,200 | 281,150 | 6% |
| Finishes & external works | 2,800,500 | 88,000 | 24,950 | 112,950 | 4% |
| Testing & commissioning | 933,500 | 12,950 | 3,800 | 16,750 | 2% |
| Total | 18,670,000 | 1,318,000 | 355,500 | 1,673,500 | 9% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Samer A. Al-Qahtani
Supervising engineer
Eng. Ibrahim A. Al-Ghamdi
Project manager
Eng. Waleed O. Al-Juhani
Finance & contracts
Khalid N. Al-Mutairi
Final approver
Dr. Abdullah S. Al-Qahtani