Certificate ⁦32⁩ — August 2026

Design & build — current HQ rehabilitation & committee-room wing

Kingdom of Saudi Arabia

Riyadh Chamber of Commerce & Industry

General Directorate of Finance & Procurement — Contracts & Procurement Department

Certificate no.
32
Date
⁦2026-09-09⁩
Hijri
27 Rabiʻ I 1448 AH
Reference
PAY-2026-007

Interim payment certificate no. (⁦32⁩)

For the work of August 2026

Contract number
RC/2024/003
Supplier-portal reference
2401220043
Contract
Design & build — current HQ rehabilitation & committee-room wing
Contractor
United Buildings & Operations Co.
Contractor VAT number
320510488360003
Project
Converting the Current Headquarters into a Member Services Centre & Committee Rooms
Contract period
⁦2024-02-01⁩ — ⁦2026-09-30⁩
Original contract value
17,600,000
Current contract value
18,670,000including variations of SAR 1.1M
Linked milestone
MEP systems installed · MS-G4 Testing & acceptance complete

Certificate summary (SAR)

1Total value of work completed to date13,445,000
2Less: previous certificates(13,090,000)
3Value of work in this certificate355,000
4Less: retention (⁦10%⁩)(35,500)
5Less: advance payment recovery (⁦10%⁩)(35,500)
6Less: delay and breach penalties0
7Total deductions(71,000)
8Net before VAT284,000
9Add: value added tax (15%)42,600
10Net amount payable to the contractor326,600

Amount in words: Three hundred twenty-six thousand six hundred Saudi riyals only

Retention held up to this certificate: SAR 1.3M — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation1,306,9001,284,80022,1001,306,900⁦100%⁩
Earthworks & foundations3,360,6003,295,95064,6503,360,600⁦100%⁩
Concrete & structural works5,787,7005,332,950143,8005,476,750⁦95%⁩
Mechanical, electrical & plumbing4,480,8002,178,30080,4502,258,750⁦50%⁩
Finishes & external works2,800,500869,90037,650907,550⁦32%⁩
Testing & commissioning933,500128,1006,350134,450⁦14%⁩
Total18,670,00013,090,000355,00013,445,000⁦72%⁩

Amounts in Saudi riyals.

Signatures and approvals

Contractor’s representative

Eng. Samer A. Al-Qahtani

Al-Qahtani⁦2026-09-09⁩

Supervising engineer

Eng. Ibrahim A. Al-Ghamdi

Al-Ghamdi⁦2026-09-11⁩

Project manager

Eng. Waleed O. Al-Juhani

Al-Juhani⁦2026-09-14⁩

Finance & contracts

Khalid N. Al-Mutairi

Al-Mutairi⁦2026-09-17⁩

Final approver

Dr. Abdullah S. Al-Qahtani

Al-Qahtani⁦2026-09-20⁩
Issued electronically through Munjaz Integration-ready for the Dynamics 365 supplier portal

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2026-09-09⁩

    Eng. Samer A. Al-Qahtani

  2. Engineer verifies quantities⁦2026-09-11⁩

    Eng. Ibrahim A. Al-Ghamdi · Director, Engineering Supervision of Construction Projects

    Took 2 days

  3. Project manager certifies⁦2026-09-14⁩

    Eng. Waleed O. Al-Juhani · Director, Facilities Operations & Maintenance

    Took 3 days

  4. Payment order prepared⁦2026-09-17⁩

    Khalid N. Al-Mutairi · Senior Finance & Procurement SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2026-09-20⁩

    Dr. Abdullah S. Al-Qahtani · Secretary-General

    Took 3 days

You are viewing as Dr. Noura M. Al-Otaibi

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneMEP systems installedLate · ⁦2026-02-28⁩
  2. Project milestoneMS-G4Testing & acceptance completeMilestone not approved yet

Deliverables & completion certificates

Not every completion certificate is issued yet — the amount tied to the milestone is not released before its deliverables are accepted.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itKhalid N. Al-Mutairi → Dr. Abdullah S. Al-Qahtani
  • Whoever verified quantities does not prepare the payment orderEng. Ibrahim A. Al-Ghamdi → Khalid N. Al-Mutairi
  • The project manager does not approve the paymentEng. Waleed O. Al-Juhani → Dr. Abdullah S. Al-Qahtani

Certificate history

20 September 2026

  1. Payment: Dr. Abdullah S. Al-Qahtani signed “Final approval”

    2026-09-20 13:00

17 September 2026

  1. Approval: Khalid N. Al-Mutairi signed “Payment order prepared”

    2026-09-17 13:00

14 September 2026

  1. Approval: Eng. Waleed O. Al-Juhani signed “Project manager certifies”

    2026-09-14 13:00

11 September 2026

  1. Approval: Eng. Ibrahim A. Al-Ghamdi signed “Engineer verifies quantities”

    2026-09-11 13:00

9 September 2026

  1. Approval: Contractor signed “Certificate submitted”

    2026-09-09 09:00
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close