AI insight
An escalated contract needs a decision
Open claims: 3; pending variations worth SAR 190K. A settlement session with the contractor is advised before deciding the next certificate.
Confidence84%
RC/2024/003
Terms, guarantees, milestones, variation orders and payment certificates.
From original to current value
Variations pending: 1 worth SAR 190K — if approved the value becomes SAR 18.9M
72% of the current value paid
Paid
13.4Mof a current value of SAR 18.7M
AI insight
Open claims: 3; pending variations worth SAR 190K. A settlement session with the contractor is advised before deciding the next certificate.
Value of each certificate
The last 14 — gross and net
Approved: 32
Count: 33 · in the approval chain: 1
| Certificate | Submitted | Gross | Retention | Deductions | VAT | Net | Status | |
|---|---|---|---|---|---|---|---|---|
| Certificate 33September 2026 | 2026-10-08 | 270K | 27K | 46K | 29.6K | 226.6K | Returned | |
| Certificate 32August 2026 | 2026-09-09 | 355K | 35.5K | 35.5K | 42.6K | 326.6K | Approved | |
| Certificate 31July 2026 | 2026-08-06 | 310K | 31K | 31K | 37.2K | 285.2K | Approved | |
| Certificate 30June 2026 | 2026-07-05 | 172K | 17.2K | 17.2K | 20.6K | 158.2K | Approved | |
| Certificate 29May 2026 | 2026-06-06 | 228.5K | 22.9K | 22.9K | 27.4K | 210.2K | Approved | |
| Certificate 28April 2026 | 2026-05-08 | 251.5K | 25.2K | 25.2K | 30.2K | 231.4K | Approved | |
| Certificate 27March 2026 | 2026-04-09 | 303K | 30.3K | 30.3K | 36.4K | 278.8K | Approved | |
| Certificate 26February 2026 | 2026-03-11 | 371K | 37.1K | 37.1K | 44.5K | 341.3K | Approved | |
| Certificate 25January 2026 | 2026-02-10 | 351.5K | 35.2K | 35.2K | 42.2K | 323.4K | Approved | |
| Certificate 24December 2025 | 2026-01-12 | 442.5K | 44.3K | 44.3K | 53.1K | 407.1K | Approved | |
| Certificate 23November 2025 | 2025-12-14 | 471.5K | 47.2K | 47.2K | 56.6K | 433.8K | Approved | |
| Certificate 22October 2025 | 2025-11-15 | 440K | 44K | 44K | 52.8K | 404.8K | Approved | |
| Certificate 21September 2025 | 2025-10-17 | 562K | 56.2K | 56.2K | 67.4K | 517K | Approved | |
| Certificate 20August 2025 | 2025-09-18 | 519.5K | 52K | 52K | 62.3K | 477.9K | Approved | |
| Certificate 19July 2025 | 2025-08-20 | 522K | 52.2K | 52.2K | 62.6K | 480.2K | Approved | |
| Certificate 18July 2025 | 2025-07-22 | 629.5K | 63K | 63K | 75.5K | 579.1K | Approved | |
| Certificate 17June 2025 | 2025-06-23 | 527.5K | 52.8K | 52.8K | 63.3K | 485.3K | Approved | |
| Certificate 16May 2025 | 2025-05-25 | 586K | 58.6K | 58.6K | 70.3K | 539.1K | Approved | |
| Certificate 15April 2025 | 2025-04-27 | 627.5K | 62.8K | 62.8K | 75.3K | 577.3K | Approved | |
| Certificate 14March 2025 | 2025-03-29 | 513.5K | 51.4K | 51.4K | 61.6K | 472.4K | Approved | |
| Certificate 13February 2025 | 2025-02-28 | 607K | 60.7K | 60.7K | 72.8K | 558.4K | Approved | |
| Certificate 12January 2025 | 2025-01-30 | 564K | 56.4K | 56.4K | 67.7K | 518.9K | Approved | |
| Certificate 11December 2024 | 2025-01-01 | 487K | 48.7K | 48.7K | 58.4K | 448K | Approved | |
| Certificate 10November 2024 | 2024-12-03 | 565K | 56.5K | 56.5K | 67.8K | 519.8K | Approved | |
| Certificate 9October 2024 | 2024-11-04 | 464.5K | 46.5K | 46.5K | 55.7K | 427.3K | Approved | |
| Certificate 8September 2024 | 2024-10-06 | 439K | 43.9K | 43.9K | 52.7K | 403.9K | Approved | |
| Certificate 7August 2024 | 2024-09-07 | 461K | 46.1K | 46.1K | 55.3K | 424.1K | Approved | |
| Certificate 6July 2024 | 2024-08-09 | 355.5K | 35.6K | 35.6K | 42.7K | 327.1K | Approved | |
| Certificate 5June 2024 | 2024-07-11 | 353.5K | 35.4K | 35.4K | 42.4K | 325.2K | Approved | |
| Certificate 4May 2024 | 2024-06-12 | 319K | 31.9K | 31.9K | 38.3K | 293.5K | Approved | |
| Certificate 3April 2024 | 2024-05-14 | 246K | 24.6K | 24.6K | 29.5K | 226.3K | Approved | |
| Certificate 2March 2024 | 2024-04-15 | 226K | 22.6K | 22.6K | 27.1K | 207.9K | Approved | |
| Certificate 1February 2024 | 2024-03-17 | 173.5K | 17.4K | 17.4K | 20.8K | 159.6K | Approved |