Riyadh ChamberMunjaz11My actionsNotifications

Certificate ⁦17⁩ — June 2025

Design & build — current HQ rehabilitation & committee-room wing

Kingdom of Saudi Arabia

Riyadh Chamber of Commerce & Industry

General Directorate of Finance & Procurement — Contracts & Procurement Department

Certificate no.
17
Date
⁦2025-06-23⁩
Hijri
27 Dhuʻl-Hijjah 1446 AH
Reference
PAY-2024-003-17

Interim payment certificate no. (⁦17⁩)

For the work of June 2025

Contract number
RC/2024/003
Supplier-portal reference
2401220043
Contract
Design & build — current HQ rehabilitation & committee-room wing
Contractor
United Buildings & Operations Co.
Contractor VAT number
320510488360003
Project
Converting the Current Headquarters into a Member Services Centre & Committee Rooms
Contract period
⁦2024-02-01⁩ — ⁦2026-09-30⁩
Original contract value
17,600,000
Current contract value
18,670,000including variations of SAR 1.1M
Linked milestone
Structure complete · MS-G3 Build complete

Certificate summary (SAR)

1Total value of work completed to date7,515,500
2Less: previous certificates(6,988,000)
3Value of work in this certificate527,500
4Less: retention (⁦10%⁩)(52,750)
5Less: advance payment recovery (⁦10%⁩)(52,750)
6Less: delay and breach penalties0
7Total deductions(105,500)
8Net before VAT422,000
9Add: value added tax (15%)63,300
10Net amount payable to the contractor485,300

Amount in words: Four hundred eighty-five thousand three hundred Saudi riyals only

Retention held up to this certificate: SAR 751.6K — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation1,306,9001,139,90073,8501,213,750⁦93%⁩
Earthworks & foundations3,360,6001,774,000119,9001,893,900⁦56%⁩
Concrete & structural works5,787,7002,381,650181,1502,562,800⁦44%⁩
Mechanical, electrical & plumbing4,480,8001,160,950101,6501,262,600⁦28%⁩
Finishes & external works2,800,500463,35043,950507,300⁦18%⁩
Testing & commissioning933,50068,1507,00075,150⁦8%⁩
Total18,670,0006,988,000527,5007,515,500⁦40%⁩

Amounts in Saudi riyals.

Signatures and approvals

Contractor’s representative

Eng. Samer A. Al-Qahtani

Al-Qahtani⁦2025-06-23⁩

Supervising engineer

Eng. Ibrahim A. Al-Ghamdi

Al-Ghamdi⁦2025-06-25⁩

Project manager

Eng. Waleed O. Al-Juhani

Al-Juhani⁦2025-06-28⁩

Finance & contracts

Khalid N. Al-Mutairi

Al-Mutairi⁦2025-07-01⁩

Final approver

Dr. Abdullah S. Al-Qahtani

Al-Qahtani⁦2025-07-04⁩
Issued electronically through Munjaz Integration-ready for the Dynamics 365 supplier portal

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2025-06-23⁩

    Eng. Samer A. Al-Qahtani

  2. Engineer verifies quantities⁦2025-06-25⁩

    Eng. Ibrahim A. Al-Ghamdi · Director, Engineering Supervision of Construction Projects

    Took 2 days

  3. Project manager certifies⁦2025-06-28⁩

    Eng. Waleed O. Al-Juhani · Director, Facilities Operations & Maintenance

    Took 3 days

  4. Payment order prepared⁦2025-07-01⁩

    Khalid N. Al-Mutairi · Senior Finance & Procurement SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2025-07-04⁩

    Dr. Abdullah S. Al-Qahtani · Secretary-General

    Took 3 days

You are viewing as Dr. Noura M. Al-Otaibi

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneStructure completeDone · ⁦2025-07-20⁩
  2. Project milestoneMS-G3Build completeMilestone approved ⁦2026-07-01⁩1 evidence file

Deliverables & completion certificates

Every linked deliverable is accepted with a completion certificate.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itKhalid N. Al-Mutairi → Dr. Abdullah S. Al-Qahtani
  • Whoever verified quantities does not prepare the payment orderEng. Ibrahim A. Al-Ghamdi → Khalid N. Al-Mutairi
  • The project manager does not approve the paymentEng. Waleed O. Al-Juhani → Dr. Abdullah S. Al-Qahtani

Certificate history

4 July 2025

  1. Payment: Dr. Abdullah S. Al-Qahtani signed “Final approval”

    2025-07-04 13:00

1 July 2025

  1. Approval: Khalid N. Al-Mutairi signed “Payment order prepared”

    2025-07-01 13:00

28 June 2025

  1. Approval: Eng. Waleed O. Al-Juhani signed “Project manager certifies”

    2025-06-28 13:00

25 June 2025

  1. Approval: Eng. Ibrahim A. Al-Ghamdi signed “Engineer verifies quantities”

    2025-06-25 13:00

23 June 2025

  1. Approval: Contractor signed “Certificate submitted”

    2025-06-23 09:00
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close