Kingdom of Saudi Arabia
Riyadh Chamber of Commerce & Industry
General Directorate of Finance & Procurement — Contracts & Procurement Department
- Certificate no.
- 20
- Date
- 2025-09-18
- Hijri
- 26 Rabiʻ I 1447 AH
- Reference
- PAY-2024-003-20
Interim payment certificate no. (20)
For the work of August 2025
- Contract number
- RC/2024/003
- Supplier-portal reference
- 2401220043
- Contract
- Design & build — current HQ rehabilitation & committee-room wing
- Contractor
- United Buildings & Operations Co.
- Contractor VAT number
- 320510488360003
- Project
- Converting the Current Headquarters into a Member Services Centre & Committee Rooms
- Contract period
- 2024-02-01 — 2026-09-30
- Original contract value
- 17,600,000
- Current contract value
- 18,670,000including variations of SAR 1.1M
- Linked milestone
- MEP systems installed · MS-G4 Testing & acceptance complete
Certificate summary (SAR)
| 1 | Total value of work completed to date | 9,186,500 |
| 2 | Less: previous certificates | (8,667,000) |
| 3 | Value of work in this certificate | 519,500 |
| 4 | Less: retention (10%) | (51,950) |
| 5 | Less: advance payment recovery (10%) | (51,950) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (103,900) |
| 8 | Net before VAT | 415,600 |
| 9 | Add: value added tax (15%) | 62,340 |
| 10 | Net amount payable to the contractor | 477,940 |
Amount in words: Four hundred seventy-seven thousand nine hundred forty Saudi riyals only
Retention held up to this certificate: SAR 918.7K — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 1,306,900 | 1,246,200 | 60,700 | 1,306,900 | 100% |
| Earthworks & foundations | 3,360,600 | 2,369,400 | 122,300 | 2,491,700 | 74% |
| Concrete & structural works | 5,787,700 | 2,953,950 | 178,650 | 3,132,600 | 54% |
| Mechanical, electrical & plumbing | 4,480,800 | 1,438,950 | 104,400 | 1,543,350 | 34% |
| Finishes & external works | 2,800,500 | 574,050 | 46,050 | 620,100 | 22% |
| Testing & commissioning | 933,500 | 84,450 | 7,400 | 91,850 | 10% |
| Total | 18,670,000 | 8,667,000 | 519,500 | 9,186,500 | 49% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Samer A. Al-Qahtani
Supervising engineer
Eng. Ibrahim A. Al-Ghamdi
Project manager
Eng. Waleed O. Al-Juhani
Finance & contracts
Khalid N. Al-Mutairi
Final approver
Dr. Abdullah S. Al-Qahtani