Certificate ⁦9⁩ — October 2024

Design & build — current HQ rehabilitation & committee-room wing

Kingdom of Saudi Arabia

Riyadh Chamber of Commerce & Industry

General Directorate of Finance & Procurement — Contracts & Procurement Department

Certificate no.
9
Date
⁦2024-11-04⁩
Hijri
2 Jumada I 1446 AH
Reference
PAY-2024-003-09

Interim payment certificate no. (⁦9⁩)

For the work of October 2024

Contract number
RC/2024/003
Supplier-portal reference
2401220043
Contract
Design & build — current HQ rehabilitation & committee-room wing
Contractor
United Buildings & Operations Co.
Contractor VAT number
320510488360003
Project
Converting the Current Headquarters into a Member Services Centre & Committee Rooms
Contract period
⁦2024-02-01⁩ — ⁦2026-09-30⁩
Original contract value
17,600,000
Current contract value
18,670,000including variations of SAR 1.1M
Linked milestone
Earthworks & foundations complete · MS-G2 Designs approved

Certificate summary (SAR)

1Total value of work completed to date3,038,000
2Less: previous certificates(2,573,500)
3Value of work in this certificate464,500
4Less: retention (⁦10%⁩)(46,450)
5Less: advance payment recovery (⁦10%⁩)(46,450)
6Less: delay and breach penalties0
7Total deductions(92,900)
8Net before VAT371,600
9Add: value added tax (15%)55,740
10Net amount payable to the contractor427,340

Amount in words: Four hundred twenty-seven thousand three hundred forty Saudi riyals only

Retention held up to this certificate: SAR 303.8K — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation1,306,900418,85071,750490,600⁦38%⁩
Earthworks & foundations3,360,600652,300113,300765,600⁦23%⁩
Concrete & structural works5,787,700877,200158,7501,035,950⁦18%⁩
Mechanical, electrical & plumbing4,480,800428,60081,800510,400⁦11%⁩
Finishes & external works2,800,500171,30033,750205,050⁦7%⁩
Testing & commissioning933,50025,2505,15030,400⁦3%⁩
Total18,670,0002,573,500464,5003,038,000⁦16%⁩

Amounts in Saudi riyals.

Signatures and approvals

Contractor’s representative

Eng. Samer A. Al-Qahtani

Al-Qahtani⁦2024-11-04⁩

Supervising engineer

Eng. Ibrahim A. Al-Ghamdi

Al-Ghamdi⁦2024-11-06⁩

Project manager

Eng. Waleed O. Al-Juhani

Al-Juhani⁦2024-11-09⁩

Finance & contracts

Khalid N. Al-Mutairi

Al-Mutairi⁦2024-11-12⁩

Final approver

Dr. Abdullah S. Al-Qahtani

Al-Qahtani⁦2024-11-15⁩
Issued electronically through Munjaz Integration-ready for the Dynamics 365 supplier portal

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2024-11-04⁩

    Eng. Samer A. Al-Qahtani

  2. Engineer verifies quantities⁦2024-11-06⁩

    Eng. Ibrahim A. Al-Ghamdi · Director, Engineering Supervision of Construction Projects

    Took 2 days

  3. Project manager certifies⁦2024-11-09⁩

    Eng. Waleed O. Al-Juhani · Director, Facilities Operations & Maintenance

    Took 3 days

  4. Payment order prepared⁦2024-11-12⁩

    Khalid N. Al-Mutairi · Senior Finance & Procurement SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2024-11-15⁩

    Dr. Abdullah S. Al-Qahtani · Secretary-General

    Took 3 days

You are viewing as Dr. Noura M. Al-Otaibi

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneEarthworks & foundations completeDone · ⁦2024-10-30⁩
  2. Project milestoneMS-G2Designs approvedMilestone approved ⁦2025-07-11⁩1 evidence file

Deliverables & completion certificates

Every linked deliverable is accepted with a completion certificate.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itKhalid N. Al-Mutairi → Dr. Abdullah S. Al-Qahtani
  • Whoever verified quantities does not prepare the payment orderEng. Ibrahim A. Al-Ghamdi → Khalid N. Al-Mutairi
  • The project manager does not approve the paymentEng. Waleed O. Al-Juhani → Dr. Abdullah S. Al-Qahtani

Certificate history

15 November 2024

  1. Payment: Dr. Abdullah S. Al-Qahtani signed “Final approval”

    2024-11-15 13:00

12 November 2024

  1. Approval: Khalid N. Al-Mutairi signed “Payment order prepared”

    2024-11-12 13:00

9 November 2024

  1. Approval: Eng. Waleed O. Al-Juhani signed “Project manager certifies”

    2024-11-09 13:00

6 November 2024

  1. Approval: Eng. Ibrahim A. Al-Ghamdi signed “Engineer verifies quantities”

    2024-11-06 13:00

4 November 2024

  1. Approval: Contractor signed “Certificate submitted”

    2024-11-04 09:00
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close