Certificate ⁦12⁩ — October 2025

Business Centre (Exit 6) branch — rehabilitation works

Kingdom of Saudi Arabia

Riyadh Chamber of Commerce & Industry

General Directorate of Finance & Procurement — Contracts & Procurement Department

Certificate no.
12
Date
⁦2025-11-10⁩
Hijri
19 Jumada I 1447 AH
Reference
PAY-2024-022-12

Interim payment certificate no. (⁦12⁩)

For the work of October 2025

Contract number
RC/2024/022
Supplier-portal reference
2402550290
Contract
Business Centre (Exit 6) branch — rehabilitation works
Contractor
United Buildings & Operations Co.
Contractor VAT number
320510488360003
Project
Business Centre (Exit 6) Branch Rehabilitation
Contract period
⁦2024-11-03⁩ — ⁦2026-10-31⁩
Original contract value
2,800,000
Current contract value
2,800,000
Linked milestone
Structure complete · MS-G3 Build complete

Certificate summary (SAR)

1Total value of work completed to date1,701,000
2Less: previous certificates(1,524,000)
3Value of work in this certificate177,000
4Less: retention (⁦10%⁩)(17,700)
5Less: advance payment recovery (⁦10%⁩)(17,700)
6Less: delay and breach penalties0
7Total deductions(35,400)
8Net before VAT141,600
9Add: value added tax (15%)21,240
10Net amount payable to the contractor162,840

Amount in words: One hundred sixty-two thousand eight hundred forty Saudi riyals only

Retention held up to this certificate: SAR 170.1K — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation196,000180,80015,200196,000⁦100%⁩
Earthworks & foundations504,000461,40042,600504,000⁦100%⁩
Concrete & structural works868,000522,15061,300583,450⁦67%⁩
Mechanical, electrical & plumbing672,000247,90037,850285,750⁦43%⁩
Finishes & external works420,00097,60017,200114,800⁦27%⁩
Testing & commissioning140,00014,1502,85017,000⁦12%⁩
Total2,800,0001,524,000177,0001,701,000⁦61%⁩

Amounts in Saudi riyals.

Signatures and approvals

Contractor’s representative

Eng. Samer A. Al-Qahtani

Al-Qahtani⁦2025-11-10⁩

Supervising engineer

Eng. Ibrahim A. Al-Ghamdi

Al-Ghamdi⁦2025-11-12⁩

Project manager

Eng. Waleed O. Al-Juhani

Al-Juhani⁦2025-11-15⁩

Finance & contracts

Khalid N. Al-Mutairi

Al-Mutairi⁦2025-11-18⁩

Final approver

Dr. Abdullah S. Al-Qahtani

Al-Qahtani⁦2025-11-21⁩
Issued electronically through Munjaz Integration-ready for the Dynamics 365 supplier portal

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2025-11-10⁩

    Eng. Samer A. Al-Qahtani

  2. Engineer verifies quantities⁦2025-11-12⁩

    Eng. Ibrahim A. Al-Ghamdi · Director, Engineering Supervision of Construction Projects

    Took 2 days

  3. Project manager certifies⁦2025-11-15⁩

    Eng. Waleed O. Al-Juhani · Director, Facilities Operations & Maintenance

    Took 3 days

  4. Payment order prepared⁦2025-11-18⁩

    Khalid N. Al-Mutairi · Senior Finance & Procurement SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2025-11-21⁩

    Dr. Abdullah S. Al-Qahtani · Secretary-General

    Took 3 days

You are viewing as Dr. Noura M. Al-Otaibi

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneStructure completeDone · ⁦2025-12-08⁩
  2. Project milestoneMS-G3Build completeMilestone approved ⁦2026-02-11⁩1 evidence file

Deliverables & completion certificates

Every linked deliverable is accepted with a completion certificate.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itKhalid N. Al-Mutairi → Dr. Abdullah S. Al-Qahtani
  • Whoever verified quantities does not prepare the payment orderEng. Ibrahim A. Al-Ghamdi → Khalid N. Al-Mutairi
  • The project manager does not approve the paymentEng. Waleed O. Al-Juhani → Dr. Abdullah S. Al-Qahtani

Certificate history

21 November 2025

  1. Payment: Dr. Abdullah S. Al-Qahtani signed “Final approval”

    2025-11-21 13:00

18 November 2025

  1. Approval: Khalid N. Al-Mutairi signed “Payment order prepared”

    2025-11-18 13:00

15 November 2025

  1. Approval: Eng. Waleed O. Al-Juhani signed “Project manager certifies”

    2025-11-15 13:00

12 November 2025

  1. Approval: Eng. Ibrahim A. Al-Ghamdi signed “Engineer verifies quantities”

    2025-11-12 13:00

10 November 2025

  1. Approval: Contractor signed “Certificate submitted”

    2025-11-10 09:00