RC/2024/022
Terms, guarantees, milestones, variation orders and payment certificates.
From original to current value
The original value and each approved variation
95% of the current value paid
Paid
2.7Mof a current value of SAR 2.8M
Value of each certificate
The last 14 — gross and net
Approved: 20
Count: 21 · in the approval chain: 1
| Certificate | Submitted | Gross | Retention | Deductions | VAT | Net | Status | |
|---|---|---|---|---|---|---|---|---|
| Certificate 21October 2026 | 2026-10-25 | 72.5K | 7,250 | 7,250 | 8,700 | 66.7K | Submitted | |
| Certificate 20June 2026 | 2026-07-08 | 140K | 14K | 14K | 16.8K | 128.8K | Approved | |
| Certificate 19May 2026 | 2026-06-06 | 58K | 5,800 | 5,800 | 6,960 | 53.4K | Approved | |
| Certificate 18April 2026 | 2026-05-07 | 85K | 8,500 | 8,500 | 10.2K | 78.2K | Approved | |
| Certificate 17March 2026 | 2026-04-08 | 94.5K | 9,450 | 9,450 | 11.3K | 86.9K | Approved | |
| Certificate 16February 2026 | 2026-03-09 | 121K | 12.1K | 12.1K | 14.5K | 111.3K | Approved | |
| Certificate 15January 2026 | 2026-02-07 | 147.5K | 14.8K | 14.8K | 17.7K | 135.7K | Approved | |
| Certificate 14December 2025 | 2026-01-08 | 137K | 13.7K | 13.7K | 16.4K | 126K | Approved | |
| Certificate 13November 2025 | 2025-12-10 | 176K | 17.6K | 17.6K | 21.1K | 161.9K | Approved | |
| Certificate 12October 2025 | 2025-11-10 | 177K | 17.7K | 17.7K | 21.2K | 162.8K | Approved | |
| Certificate 11September 2025 | 2025-10-11 | 162.5K | 16.3K | 16.3K | 19.5K | 149.5K | Approved | |
| Certificate 10August 2025 | 2025-09-12 | 200.5K | 20.1K | 20.1K | 24.1K | 184.5K | Approved | |
| Certificate 9July 2025 | 2025-08-13 | 171K | 17.1K | 17.1K | 20.5K | 157.3K | Approved | |
| Certificate 8June 2025 | 2025-07-14 | 166.5K | 16.7K | 16.7K | 20K | 153.2K | Approved | |
| Certificate 7May 2025 | 2025-06-14 | 182K | 18.2K | 18.2K | 21.8K | 167.4K | Approved | |
| Certificate 6April 2025 | 2025-05-16 | 139K | 13.9K | 13.9K | 16.7K | 127.9K | Approved | |
| Certificate 5March 2025 | 2025-04-16 | 141K | 14.1K | 14.1K | 16.9K | 129.7K | Approved | |
| Certificate 4February 2025 | 2025-03-17 | 127K | 12.7K | 12.7K | 15.2K | 116.8K | Approved | |
| Certificate 3January 2025 | 2025-02-15 | 93K | 9,300 | 9,300 | 11.2K | 85.6K | Approved | |
| Certificate 2December 2024 | 2025-01-17 | 83.5K | 8,350 | 8,350 | 10K | 76.8K | Approved | |
| Certificate 1November 2024 | 2024-12-18 | 58K | 5,800 | 5,800 | 6,960 | 53.4K | Approved |