Kingdom of Saudi Arabia
Riyadh Chamber of Commerce & Industry
General Directorate of Finance & Procurement — Contracts & Procurement Department
- Certificate no.
- 2
- Date
- 2025-01-17
- Hijri
- 17 Rajab 1446 AH
- Reference
- PAY-2024-022-02
Interim payment certificate no. (2)
For the work of December 2024
- Contract number
- RC/2024/022
- Supplier-portal reference
- 2402550290
- Contract
- Business Centre (Exit 6) branch — rehabilitation works
- Contractor
- United Buildings & Operations Co.
- Contractor VAT number
- 320510488360003
- Project
- Business Centre (Exit 6) Branch Rehabilitation
- Contract period
- 2024-11-03 — 2026-10-31
- Original contract value
- 2,800,000
- Current contract value
- 2,800,000
- Linked milestone
- Earthworks & foundations complete · MS-G2 Designs approved
Certificate summary (SAR)
| 1 | Total value of work completed to date | 141,500 |
| 2 | Less: previous certificates | (58,000) |
| 3 | Value of work in this certificate | 83,500 |
| 4 | Less: retention (10%) | (8,350) |
| 5 | Less: advance payment recovery (10%) | (8,350) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (16,700) |
| 8 | Net before VAT | 66,800 |
| 9 | Add: value added tax (15%) | 10,020 |
| 10 | Net amount payable to the contractor | 76,820 |
Amount in words: Seventy-six thousand eight hundred twenty Saudi riyals only
Retention held up to this certificate: SAR 14.2K — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 196,000 | 9,550 | 13,350 | 22,900 | 12% |
| Earthworks & foundations | 504,000 | 14,800 | 20,850 | 35,650 | 7% |
| Concrete & structural works | 868,000 | 19,750 | 28,500 | 48,250 | 6% |
| Mechanical, electrical & plumbing | 672,000 | 9,550 | 14,200 | 23,750 | 4% |
| Finishes & external works | 420,000 | 3,800 | 5,750 | 9,550 | 2% |
| Testing & commissioning | 140,000 | 550 | 850 | 1,400 | 1% |
| Total | 2,800,000 | 58,000 | 83,500 | 141,500 | 5% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Samer A. Al-Qahtani
Supervising engineer
Eng. Ibrahim A. Al-Ghamdi
Project manager
Eng. Waleed O. Al-Juhani
Finance & contracts
Khalid N. Al-Mutairi
Final approver
Dr. Abdullah S. Al-Qahtani