Kingdom of Saudi Arabia
Riyadh Chamber of Commerce & Industry
General Directorate of Finance & Procurement — Contracts & Procurement Department
- Certificate no.
- 19
- Date
- 2026-06-06
- Hijri
- 20 Dhuʻl-Hijjah 1447 AH
- Reference
- PAY-2024-022-19
Interim payment certificate no. (19)
For the work of May 2026
- Contract number
- RC/2024/022
- Supplier-portal reference
- 2402550290
- Contract
- Business Centre (Exit 6) branch — rehabilitation works
- Contractor
- United Buildings & Operations Co.
- Contractor VAT number
- 320510488360003
- Project
- Business Centre (Exit 6) Branch Rehabilitation
- Contract period
- 2024-11-03 — 2026-10-31
- Original contract value
- 2,800,000
- Current contract value
- 2,800,000
- Linked milestone
- Testing & commissioning · MS-G5 Final handover
Certificate summary (SAR)
| 1 | Total value of work completed to date | 2,520,000 |
| 2 | Less: previous certificates | (2,462,000) |
| 3 | Value of work in this certificate | 58,000 |
| 4 | Less: retention (10%) | (5,800) |
| 5 | Less: advance payment recovery (10%) | (5,800) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (11,600) |
| 8 | Net before VAT | 46,400 |
| 9 | Add: value added tax (15%) | 6,960 |
| 10 | Net amount payable to the contractor | 53,360 |
Amount in words: Fifty-three thousand three hundred sixty Saudi riyals only
Retention held up to this certificate: SAR 252K — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 196,000 | 194,350 | 1,650 | 196,000 | 100% |
| Earthworks & foundations | 504,000 | 498,300 | 5,700 | 504,000 | 100% |
| Concrete & structural works | 868,000 | 850,350 | 17,650 | 868,000 | 100% |
| Mechanical, electrical & plumbing | 672,000 | 650,300 | 21,700 | 672,000 | 100% |
| Finishes & external works | 420,000 | 244,650 | 10,150 | 254,800 | 61% |
| Testing & commissioning | 140,000 | 24,050 | 1,150 | 25,200 | 18% |
| Total | 2,800,000 | 2,462,000 | 58,000 | 2,520,000 | 90% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Samer A. Al-Qahtani
Supervising engineer
Eng. Ibrahim A. Al-Ghamdi
Project manager
Eng. Waleed O. Al-Juhani
Finance & contracts
Khalid N. Al-Mutairi
Final approver
Dr. Abdullah S. Al-Qahtani