Riyadh ChamberMunjaz11My actionsNotifications

Certificate ⁦19⁩ — May 2026

Business Centre (Exit 6) branch — rehabilitation works

Kingdom of Saudi Arabia

Riyadh Chamber of Commerce & Industry

General Directorate of Finance & Procurement — Contracts & Procurement Department

Certificate no.
19
Date
⁦2026-06-06⁩
Hijri
20 Dhuʻl-Hijjah 1447 AH
Reference
PAY-2024-022-19

Interim payment certificate no. (⁦19⁩)

For the work of May 2026

Contract number
RC/2024/022
Supplier-portal reference
2402550290
Contract
Business Centre (Exit 6) branch — rehabilitation works
Contractor
United Buildings & Operations Co.
Contractor VAT number
320510488360003
Project
Business Centre (Exit 6) Branch Rehabilitation
Contract period
⁦2024-11-03⁩ — ⁦2026-10-31⁩
Original contract value
2,800,000
Current contract value
2,800,000
Linked milestone
Testing & commissioning · MS-G5 Final handover

Certificate summary (SAR)

1Total value of work completed to date2,520,000
2Less: previous certificates(2,462,000)
3Value of work in this certificate58,000
4Less: retention (⁦10%⁩)(5,800)
5Less: advance payment recovery (⁦10%⁩)(5,800)
6Less: delay and breach penalties0
7Total deductions(11,600)
8Net before VAT46,400
9Add: value added tax (15%)6,960
10Net amount payable to the contractor53,360

Amount in words: Fifty-three thousand three hundred sixty Saudi riyals only

Retention held up to this certificate: SAR 252K — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation196,000194,3501,650196,000⁦100%⁩
Earthworks & foundations504,000498,3005,700504,000⁦100%⁩
Concrete & structural works868,000850,35017,650868,000⁦100%⁩
Mechanical, electrical & plumbing672,000650,30021,700672,000⁦100%⁩
Finishes & external works420,000244,65010,150254,800⁦61%⁩
Testing & commissioning140,00024,0501,15025,200⁦18%⁩
Total2,800,0002,462,00058,0002,520,000⁦90%⁩

Amounts in Saudi riyals.

Signatures and approvals

Contractor’s representative

Eng. Samer A. Al-Qahtani

Al-Qahtani⁦2026-06-06⁩

Supervising engineer

Eng. Ibrahim A. Al-Ghamdi

Al-Ghamdi⁦2026-06-08⁩

Project manager

Eng. Waleed O. Al-Juhani

Al-Juhani⁦2026-06-11⁩

Finance & contracts

Khalid N. Al-Mutairi

Al-Mutairi⁦2026-06-14⁩

Final approver

Dr. Abdullah S. Al-Qahtani

Al-Qahtani⁦2026-06-17⁩
Issued electronically through Munjaz Integration-ready for the Dynamics 365 supplier portal

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2026-06-06⁩

    Eng. Samer A. Al-Qahtani

  2. Engineer verifies quantities⁦2026-06-08⁩

    Eng. Ibrahim A. Al-Ghamdi · Director, Engineering Supervision of Construction Projects

    Took 2 days

  3. Project manager certifies⁦2026-06-11⁩

    Eng. Waleed O. Al-Juhani · Director, Facilities Operations & Maintenance

    Took 3 days

  4. Payment order prepared⁦2026-06-14⁩

    Khalid N. Al-Mutairi · Senior Finance & Procurement SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2026-06-17⁩

    Dr. Abdullah S. Al-Qahtani · Secretary-General

    Took 3 days

You are viewing as Dr. Noura M. Al-Otaibi

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneTesting & commissioningDone · ⁦2026-09-03⁩
  2. Project milestoneMS-G5Final handoverMilestone not approved yet

Deliverables & completion certificates

Every linked deliverable is accepted with a completion certificate.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itKhalid N. Al-Mutairi → Dr. Abdullah S. Al-Qahtani
  • Whoever verified quantities does not prepare the payment orderEng. Ibrahim A. Al-Ghamdi → Khalid N. Al-Mutairi
  • The project manager does not approve the paymentEng. Waleed O. Al-Juhani → Dr. Abdullah S. Al-Qahtani

Certificate history

17 June 2026

  1. Payment: Dr. Abdullah S. Al-Qahtani signed “Final approval”

    2026-06-17 13:00

14 June 2026

  1. Approval: Khalid N. Al-Mutairi signed “Payment order prepared”

    2026-06-14 13:00

11 June 2026

  1. Approval: Eng. Waleed O. Al-Juhani signed “Project manager certifies”

    2026-06-11 13:00

8 June 2026

  1. Approval: Eng. Ibrahim A. Al-Ghamdi signed “Engineer verifies quantities”

    2026-06-08 13:00

6 June 2026

  1. Approval: Contractor signed “Certificate submitted”

    2026-06-06 09:00
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close