Certificate ⁦3⁩ — January 2025

Business Centre (Exit 6) branch — rehabilitation works

Kingdom of Saudi Arabia

Riyadh Chamber of Commerce & Industry

General Directorate of Finance & Procurement — Contracts & Procurement Department

Certificate no.
3
Date
⁦2025-02-15⁩
Hijri
16 Shaʻban 1446 AH
Reference
PAY-2024-022-03

Interim payment certificate no. (⁦3⁩)

For the work of January 2025

Contract number
RC/2024/022
Supplier-portal reference
2402550290
Contract
Business Centre (Exit 6) branch — rehabilitation works
Contractor
United Buildings & Operations Co.
Contractor VAT number
320510488360003
Project
Business Centre (Exit 6) Branch Rehabilitation
Contract period
⁦2024-11-03⁩ — ⁦2026-10-31⁩
Original contract value
2,800,000
Current contract value
2,800,000
Linked milestone
Earthworks & foundations complete · MS-G2 Designs approved

Certificate summary (SAR)

1Total value of work completed to date234,500
2Less: previous certificates(141,500)
3Value of work in this certificate93,000
4Less: retention (⁦10%⁩)(9,300)
5Less: advance payment recovery (⁦10%⁩)(9,300)
6Less: delay and breach penalties0
7Total deductions(18,600)
8Net before VAT74,400
9Add: value added tax (15%)11,160
10Net amount payable to the contractor85,560

Amount in words: Eighty-five thousand five hundred sixty Saudi riyals only

Retention held up to this certificate: SAR 23.5K — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation196,00023,15014,70037,850⁦19%⁩
Earthworks & foundations504,00036,05023,05059,100⁦12%⁩
Concrete & structural works868,00048,20031,75079,950⁦9%⁩
Mechanical, electrical & plumbing672,00023,40016,00039,400⁦6%⁩
Finishes & external works420,0009,3506,50015,850⁦4%⁩
Testing & commissioning140,0001,3501,0002,350⁦2%⁩
Total2,800,000141,50093,000234,500⁦8%⁩

Amounts in Saudi riyals.

Signatures and approvals

Contractor’s representative

Eng. Samer A. Al-Qahtani

Al-Qahtani⁦2025-02-15⁩

Supervising engineer

Eng. Ibrahim A. Al-Ghamdi

Al-Ghamdi⁦2025-02-17⁩

Project manager

Eng. Waleed O. Al-Juhani

Al-Juhani⁦2025-02-20⁩

Finance & contracts

Khalid N. Al-Mutairi

Al-Mutairi⁦2025-02-23⁩

Final approver

Dr. Abdullah S. Al-Qahtani

Al-Qahtani⁦2025-02-26⁩
Issued electronically through Munjaz Integration-ready for the Dynamics 365 supplier portal

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2025-02-15⁩

    Eng. Samer A. Al-Qahtani

  2. Engineer verifies quantities⁦2025-02-17⁩

    Eng. Ibrahim A. Al-Ghamdi · Director, Engineering Supervision of Construction Projects

    Took 2 days

  3. Project manager certifies⁦2025-02-20⁩

    Eng. Waleed O. Al-Juhani · Director, Facilities Operations & Maintenance

    Took 3 days

  4. Payment order prepared⁦2025-02-23⁩

    Khalid N. Al-Mutairi · Senior Finance & Procurement SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2025-02-26⁩

    Dr. Abdullah S. Al-Qahtani · Secretary-General

    Took 3 days

You are viewing as Dr. Noura M. Al-Otaibi

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneEarthworks & foundations completeDone · ⁦2025-05-26⁩
  2. Project milestoneMS-G2Designs approvedMilestone approved ⁦2025-07-31⁩1 evidence file

Deliverables & completion certificates

Every linked deliverable is accepted with a completion certificate.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itKhalid N. Al-Mutairi → Dr. Abdullah S. Al-Qahtani
  • Whoever verified quantities does not prepare the payment orderEng. Ibrahim A. Al-Ghamdi → Khalid N. Al-Mutairi
  • The project manager does not approve the paymentEng. Waleed O. Al-Juhani → Dr. Abdullah S. Al-Qahtani

Certificate history

26 February 2025

  1. Payment: Dr. Abdullah S. Al-Qahtani signed “Final approval”

    2025-02-26 13:00

23 February 2025

  1. Approval: Khalid N. Al-Mutairi signed “Payment order prepared”

    2025-02-23 13:00

20 February 2025

  1. Approval: Eng. Waleed O. Al-Juhani signed “Project manager certifies”

    2025-02-20 13:00

17 February 2025

  1. Approval: Eng. Ibrahim A. Al-Ghamdi signed “Engineer verifies quantities”

    2025-02-17 13:00

15 February 2025

  1. Approval: Contractor signed “Certificate submitted”

    2025-02-15 09:00
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close