Kingdom of Saudi Arabia
Riyadh Chamber of Commerce & Industry
General Directorate of Finance & Procurement — Contracts & Procurement Department
- Certificate no.
- 11
- Date
- 2026-08-07
- Hijri
- 24 Safar 1448 AH
- Reference
- PAY-2025-006-11
Interim payment certificate no. (11)
For the work of July 2026
- Contract number
- RC/2025/006
- Supplier-portal reference
- 2503530472
- Contract
- Disaster recovery site — civil & MEP fit-out
- Contractor
- Al-Ufuq General Contracting Co.
- Contractor VAT number
- 320500924170003
- Project
- Disaster Recovery Centre for the Chamber’s Systems
- Contract period
- 2025-05-04 — 2026-11-30
- Original contract value
- 4,600,000
- Current contract value
- 4,755,000including variations of SAR 155K
- Linked milestone
- MEP systems installed · MS-G4 Testing & acceptance complete
Certificate summary (SAR)
| 1 | Total value of work completed to date | 3,310,000 |
| 2 | Less: previous certificates | (3,166,000) |
| 3 | Value of work in this certificate | 144,000 |
| 4 | Less: retention (10%) | (14,400) |
| 5 | Less: advance payment recovery (10%) | (14,400) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (28,800) |
| 8 | Net before VAT | 115,200 |
| 9 | Add: value added tax (15%) | 17,280 |
| 10 | Net amount payable to the contractor | 132,480 |
Amount in words: One hundred thirty-two thousand four hundred eighty Saudi riyals only
Retention held up to this certificate: SAR 331K — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 332,850 | 323,200 | 9,650 | 332,850 | 100% |
| Earthworks & foundations | 855,900 | 828,050 | 27,850 | 855,900 | 100% |
| Concrete & structural works | 1,474,050 | 1,251,800 | 56,800 | 1,308,600 | 89% |
| Mechanical, electrical & plumbing | 1,141,200 | 523,900 | 32,200 | 556,100 | 49% |
| Finishes & external works | 713,250 | 208,500 | 14,950 | 223,450 | 31% |
| Testing & commissioning | 237,750 | 30,550 | 2,550 | 33,100 | 14% |
| Total | 4,755,000 | 3,166,000 | 144,000 | 3,310,000 | 70% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Khalil I. Al-Dosari
Supervising engineer
Eng. Ibrahim A. Al-Ghamdi
Project manager
Eng. Omar H. Bawazir
Finance & contracts
Khalid N. Al-Mutairi
Final approver
Dr. Abdullah S. Al-Qahtani