RC/2025/006
Terms, guarantees, milestones, variation orders and payment certificates.
From original to current value
The original value and each approved variation
75% of the current value paid
Paid
3.6Mof a current value of SAR 4.8M
Value of each certificate
The last 13 — gross and net
Approved: 12
Count: 13 · in the approval chain: 1
| Certificate | Submitted | Gross | Retention | Deductions | VAT | Net | Status | |
|---|---|---|---|---|---|---|---|---|
| Certificate 13September 2026 | 2026-10-11 | 245K | 24.5K | 24.5K | 29.4K | 225.4K | In review | |
| Certificate 12August 2026 | 2026-09-08 | 280K | 28K | 28K | 33.6K | 257.6K | Approved | |
| Certificate 11July 2026 | 2026-08-07 | 144K | 14.4K | 14.4K | 17.3K | 132.5K | Approved | |
| Certificate 10June 2026 | 2026-06-27 | 251K | 25.1K | 25.1K | 30.1K | 230.9K | Approved | |
| Certificate 9April 2026 | 2026-05-16 | 292.5K | 29.3K | 29.3K | 35.1K | 269.1K | Approved | |
| Certificate 8March 2026 | 2026-04-05 | 347.5K | 34.8K | 34.8K | 41.7K | 319.7K | Approved | |
| Certificate 7February 2026 | 2026-02-22 | 439.5K | 44K | 44K | 52.7K | 404.3K | Approved | |
| Certificate 6December 2025 | 2026-01-12 | 370.5K | 37.1K | 37.1K | 44.5K | 340.9K | Approved | |
| Certificate 5November 2025 | 2025-12-01 | 408K | 40.8K | 40.8K | 49K | 375.4K | Approved | |
| Certificate 4October 2025 | 2025-10-21 | 384.5K | 38.5K | 38.5K | 46.1K | 353.7K | Approved | |
| Certificate 3August 2025 | 2025-09-09 | 276K | 27.6K | 27.6K | 33.1K | 253.9K | Approved | |
| Certificate 2July 2025 | 2025-07-30 | 247K | 24.7K | 24.7K | 29.6K | 227.2K | Approved | |
| Certificate 1May 2025 | 2025-06-18 | 149.5K | 15K | 15K | 17.9K | 137.5K | Approved |