Riyadh ChamberMunjaz11My actionsNotifications
PRJ-2026-003At risk4ExecutionWaterfallIn progress

Disaster Recovery Centre for the Chamber’s Systems

Add to watchlist

A Tier III standby site at a licensed provider in Al-Kharj that keeps the My Business portal, e-attestation and the chamber’s systems running after a major outage.

Early warning: ⁦63%⁩ chance of slipping within ⁦45⁩ days

Budget (BAC)

SAR 7.4M

Actual cost

SAR 5.9M

⁦79%⁩ of budget

Progress

⁦72%⁩Awaiting acceptance ⁦8%⁩

Estimate at completion

SAR 8.1M

SAR +732K

SPI · CPI

0.90Schedule performance index · 0.900.91Cost performance index · 0.91

Forecast finish

⁦2027-01-07⁩

38 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure13 October 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate5 February 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionConditional goDate6 April 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate11 July 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate13 October 2026Closure · Not startedClosure · Not started

Project health across eight dimensions

A weighted index, not just percent complete; each dimension leads to the tab that explains it.

Index over the last six reports

−9

May to October 2026

No material change in the health dimensions over the period.

AI insight

⁦63%⁩ chance of a further slip within ⁦45⁩ days

From the SPI trend (⁦0.90⁩), the task closure rate and the open risks, the early-warning engine expects another slip unless the resource gap is closed.

Confidence⁦82%⁩

Copilot summary

Generated from the live project data

The project is behind plan: ⁦72% done against 80% planned⁩.

⁦SPI 0⁩.⁦90⁩, ⁦CPI 0⁩.⁦91⁩.

The project’s link, progress and status

How the project ties to the strategy, its progress counted from accepted deliverables, and its status history.

Strategic link

The main objective and initiative, the secondary links, and the project’s contribution to its initiative.

Main strategic objective· Axis: Improving the OrganisationSO-4.2Streamlined governance and dependable technology

Main initiative

SI-4.2.1Cloud & cybersecurity

Contribution to the initiative⁦62%⁩

The project’s share of the initiative’s project budget (3 projects)

Secondary links

No secondary links

Annual work-plan line
WP-2025-003
Classification
Operational

Project progress from accepted deliverables

Project progress = the sum of the weights of deliverables accepted with a completion certificate; nothing counts before acceptance.

Counted

⁦72%⁩

Awaiting acceptance ⁦8%⁩

Not handed in ⁦20%⁩

7 deliverables accepted

  • Release 1⁦15%⁩
  • Release 2⁦15%⁩
  • Integrations⁦15%⁩
  • Business requirements⁦9%⁩
  • Solution design⁦9%⁩
  • Project plan & baseline⁦5%⁩
  • Monitoring & reporting⁦4%⁩

1 deliverable under inspection or acceptance

  • System testing⁦8%⁩

Progress & earned value

⁦3⁩ of ⁦5⁩ milestones complete

Earned-value curve

Planned, earned and actual to the data date, cumulative, with the forecast cost tail

  • Planned value
  • Earned value
  • Actual cost
  • Estimate at completion
  • Budget at completion

Budget & commitments

Commitments are ⁦94%⁩ of budget

5.9M/ 7.4M732Kprojected overrun(⁦9.9%⁩)
Actual spend
5.9M
Committed
7M
Approved budget
7.4M
Estimate at completion
8.1M

Next milestones

  • Provisional acceptance⁦2026-11-11⁩was ⁦2026-10-13⁩Late
  • Closure⁦2027-01-07⁩was ⁦2026-11-30⁩Late

Waiting on someone

⁦1⁩ approval and ⁦0⁩ open actions on this project

Approvals & requests

From «My actions» for this project

Actions

⁦0⁩ open

  • No actions on this project

Risks & impediments

2 open risks, exposure SAR 530K

Risk map

Probability
5Probability: Almost certain · Impact: NegligibleLow · Score ⁦5⁩Probability: Almost certain · Impact: MinorMedium · Score ⁦10⁩Probability: Almost certain · Impact: ModerateHigh · Score ⁦15⁩Probability: Almost certain · Impact: MajorCritical · Score ⁦20⁩Probability: Almost certain · Impact: SevereCritical · Score ⁦25⁩
4Probability: Likely · Impact: NegligibleLow · Score ⁦4⁩Probability: Likely · Impact: MinorMedium · Score ⁦8⁩1Probability: Likely · Impact: ModerateMedium · Score ⁦12⁩RSK-0020Late delivery of cooling units and standby generators1Probability: Likely · Impact: MajorHigh · Score ⁦16⁩RSK-0019Exchange-rate swings on imported equipment without fixed pricesProbability: Likely · Impact: SevereCritical · Score ⁦20⁩
3Probability: Possible · Impact: NegligibleLow · Score ⁦3⁩Probability: Possible · Impact: MinorLow · Score ⁦6⁩Probability: Possible · Impact: ModerateMedium · Score ⁦9⁩Probability: Possible · Impact: MajorMedium · Score ⁦12⁩Probability: Possible · Impact: SevereHigh · Score ⁦15⁩
2Probability: Unlikely · Impact: NegligibleLow · Score ⁦2⁩Probability: Unlikely · Impact: MinorLow · Score ⁦4⁩Probability: Unlikely · Impact: ModerateLow · Score ⁦6⁩Probability: Unlikely · Impact: MajorMedium · Score ⁦8⁩Probability: Unlikely · Impact: SevereMedium · Score ⁦10⁩
1Probability: Rare · Impact: NegligibleLow · Score ⁦1⁩Probability: Rare · Impact: MinorLow · Score ⁦2⁩Probability: Rare · Impact: ModerateLow · Score ⁦3⁩Probability: Rare · Impact: MajorLow · Score ⁦4⁩Probability: Rare · Impact: SevereLow · Score ⁦5⁩
12345

Impact

  • Critical0
  • High1
  • Medium1
  • Low0

Deliverables

⁦7⁩ of ⁦11⁩ approved

  • Project plan & baseline003-D1 · V1 · CRT-003-01⁦5%⁩Eng. Omar H. Bawazir⁦2025-06-28⁩2025-06-283 Muharram 1447 AHApproved
  • Monitoring & reporting003-D2 · V1 · CRT-003-02⁦4%⁩Eng. Nayef H. Al-Buqami⁦2025-08-19⁩2025-08-1925 Safar 1447 AHApproved
  • Business requirements003-D3 · V1 · CRT-003-03⁦9%⁩Eng. Nayef H. Al-Buqami⁦2025-10-10⁩2025-10-1018 Rabiʻ II 1447 AHApproved
  • Solution design003-D4 · V1 · CRT-003-04⁦9%⁩Eng. Majed S. Al-Rasheed⁦2025-12-01⁩2025-12-0110 Jumada II 1447 AHApproved
  • Release 1003-D5 · V1 · CRT-003-05⁦15%⁩Eng. Majed S. Al-Rasheed⁦2026-01-22⁩2026-01-223 Shaʻban 1447 AHApproved
  • Release 2003-D6 · V1 · CRT-003-06⁦15%⁩Eng. Omar H. Bawazir⁦2026-03-15⁩2026-03-1526 Ramadan 1447 AHApproved
  • Integrations003-D7 · V1 · CRT-003-07⁦15%⁩Eng. Nayef H. Al-Buqami⁦2026-05-06⁩2026-05-0619 Dhuʻl-Qiʻdah 1447 AHApproved
  • System testing003-D8 · V1⁦8%⁩Eng. Omar H. Bawazir123 days overdue2026-06-2712 Muharram 1448 AHIn review
  • User acceptance testing003-D9 · V0⁦8%⁩Eng. Nayef H. Al-Buqami71 days overdue2026-08-185 Rabiʻ I 1448 AHDraft
  • Training & change003-D10 · V0⁦6%⁩Eng. Nayef H. Al-Buqami19 days overdue2026-10-0928 Rabiʻ II 1448 AHDraft
  • Go-live & handover003-D11 · V0⁦6%⁩Eng. Majed S. Al-RasheedIn 33 days2026-11-3020 Jumada II 1448 AHDraft

Team, contracts & documents

Team

2 members

Eng. Omar H. Bawazir · Director, IT InfrastructureEng. Nayef H. Al-Buqami · Director General, Information Technology
  • Eng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureProject managerP-024o.bawazir@chamber.sa⁦40%⁩
  • Eng. Nayef H. Al-BuqamiEng. Nayef H. Al-BuqamiDirector General, Information TechnologyProject ownerP-017n.albuqami@chamber.sa⁦20%⁩

Documents

  • No documents yet

Meetings

  • No meetings scheduled
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close