Original
Original baseline
- Finish
- 2026-11-30
- Budget
- SAR 7.2M
- 16 activities
Approved with the project plan at the planning gate.
Approved 2025-04-06 · by Eng. Majed S. Al-Rasheed
A Tier III standby site at a licensed provider in Al-Kharj that keeps the My Business portal, e-attestation and the chamber’s systems running after a major outage.
Budget (BAC)
Actual cost
79% of budget
Progress
Estimate at completion
SAR +732K
SPI · CPI
Forecast finish
38 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure13 October 2026
The original, the approved revised and the working baseline, with any two versions compared on dates and cost. An approved baseline is locked and moves only through a change request; every version is kept.
Original
Approved with the project plan at the planning gate.
Approved 2025-04-06 · by Eng. Majed S. Al-Rasheed
Working
Follows the latest schedule and cost forecast; becomes approved only through a change request the CCB passes.
Created 2026-10-28 · by Eng. Omar H. Bawazir
What changed from version A to version B
Finish
2026-11-302027-01-09
+40 days
Budget
SAR 7.2MSAR 7.4M
+0.16 SAR M
Milestones moved
5 / 5
Each line starts at the milestone’s date in A and ends at its date in B
Version AVersion B
Difference in SAR millions from A to B
Every saved version with its reason and reference