Kingdom of Saudi Arabia
Riyadh Chamber of Commerce & Industry
General Directorate of Finance & Procurement — Contracts & Procurement Department
- Certificate no.
- 8
- Date
- 2026-04-05
- Hijri
- 17 Shawwal 1447 AH
- Reference
- PAY-2025-006-08
Interim payment certificate no. (8)
For the work of March 2026
- Contract number
- RC/2025/006
- Supplier-portal reference
- 2503530472
- Contract
- Disaster recovery site — civil & MEP fit-out
- Contractor
- Al-Ufuq General Contracting Co.
- Contractor VAT number
- 320500924170003
- Project
- Disaster Recovery Centre for the Chamber’s Systems
- Contract period
- 2025-05-04 — 2026-11-30
- Original contract value
- 4,600,000
- Current contract value
- 4,755,000including variations of SAR 155K
- Linked milestone
- MEP systems installed · MS-G4 Testing & acceptance complete
Certificate summary (SAR)
| 1 | Total value of work completed to date | 2,622,500 |
| 2 | Less: previous certificates | (2,275,000) |
| 3 | Value of work in this certificate | 347,500 |
| 4 | Less: retention (10%) | (34,750) |
| 5 | Less: advance payment recovery (10%) | (34,750) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (69,500) |
| 8 | Net before VAT | 278,000 |
| 9 | Add: value added tax (15%) | 41,700 |
| 10 | Net amount payable to the contractor | 319,700 |
Amount in words: Three hundred nineteen thousand seven hundred Saudi riyals only
Retention held up to this certificate: SAR 262.3K — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 332,850 | 298,200 | 34,650 | 332,850 | 100% |
| Earthworks & foundations | 855,900 | 667,800 | 83,750 | 751,550 | 88% |
| Concrete & structural works | 1,474,050 | 774,650 | 119,600 | 894,250 | 61% |
| Mechanical, electrical & plumbing | 1,141,200 | 368,600 | 72,000 | 440,600 | 39% |
| Finishes & external works | 713,250 | 144,800 | 32,200 | 177,000 | 25% |
| Testing & commissioning | 237,750 | 20,950 | 5,300 | 26,250 | 11% |
| Total | 4,755,000 | 2,275,000 | 347,500 | 2,622,500 | 55% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Khalil I. Al-Dosari
Supervising engineer
Eng. Ibrahim A. Al-Ghamdi
Project manager
Eng. Omar H. Bawazir
Finance & contracts
Khalid N. Al-Mutairi
Final approver
Dr. Abdullah S. Al-Qahtani