Kingdom of Saudi Arabia
Riyadh Chamber of Commerce & Industry
General Directorate of Finance & Procurement — Contracts & Procurement Department
- Certificate no.
- 6
- Date
- 2026-01-12
- Hijri
- 23 Rajab 1447 AH
- Reference
- PAY-2025-006-06
Interim payment certificate no. (6)
For the work of December 2025
- Contract number
- RC/2025/006
- Supplier-portal reference
- 2503530472
- Contract
- Disaster recovery site — civil & MEP fit-out
- Contractor
- Al-Ufuq General Contracting Co.
- Contractor VAT number
- 320500924170003
- Project
- Disaster Recovery Centre for the Chamber’s Systems
- Contract period
- 2025-05-04 — 2026-11-30
- Original contract value
- 4,600,000
- Current contract value
- 4,755,000including variations of SAR 155K
- Linked milestone
- Structure complete · MS-G3 Build complete
Certificate summary (SAR)
| 1 | Total value of work completed to date | 1,835,500 |
| 2 | Less: previous certificates | (1,465,000) |
| 3 | Value of work in this certificate | 370,500 |
| 4 | Less: retention (10%) | (37,050) |
| 5 | Less: advance payment recovery (10%) | (37,050) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (74,100) |
| 8 | Net before VAT | 296,400 |
| 9 | Add: value added tax (15%) | 44,460 |
| 10 | Net amount payable to the contractor | 340,860 |
Amount in words: Three hundred forty thousand eight hundred sixty Saudi riyals only
Retention held up to this certificate: SAR 183.6K — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 332,850 | 244,150 | 52,300 | 296,450 | 89% |
| Earthworks & foundations | 855,900 | 377,800 | 84,750 | 462,550 | 54% |
| Concrete & structural works | 1,474,050 | 498,700 | 127,200 | 625,900 | 42% |
| Mechanical, electrical & plumbing | 1,141,200 | 237,450 | 70,900 | 308,350 | 27% |
| Finishes & external works | 713,250 | 93,350 | 30,550 | 123,900 | 17% |
| Testing & commissioning | 237,750 | 13,550 | 4,800 | 18,350 | 8% |
| Total | 4,755,000 | 1,465,000 | 370,500 | 1,835,500 | 39% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Khalil I. Al-Dosari
Supervising engineer
Eng. Ibrahim A. Al-Ghamdi
Project manager
Eng. Omar H. Bawazir
Finance & contracts
Khalid N. Al-Mutairi
Final approver
Dr. Abdullah S. Al-Qahtani