Kingdom of Saudi Arabia
Riyadh Chamber of Commerce & Industry
General Directorate of Finance & Procurement — Contracts & Procurement Department
- Certificate no.
- 4
- Date
- 2025-11-27
- Hijri
- 6 Jumada II 1447 AH
- Reference
- PAY-2025-012-04
Interim payment certificate no. (4)
For the work of November 2025
- Contract number
- RC/2025/012
- Supplier-portal reference
- 2503950550
- Contract
- Network & server equipment — disaster recovery site
- Contractor
- Smart Link Telecom & Security Systems Co.
- Contractor VAT number
- 340303165720003
- Project
- Disaster Recovery Centre for the Chamber’s Systems
- Contract period
- 2025-06-01 — 2026-11-30
- Original contract value
- 1,900,000
- Current contract value
- 1,900,000
- Linked milestone
- Structure complete · MS-G3 Build complete
Certificate summary (SAR)
| 1 | Total value of work completed to date | 391,500 |
| 2 | Less: previous certificates | (249,000) |
| 3 | Value of work in this certificate | 142,500 |
| 4 | Less: retention (5%) | (7,125) |
| 5 | Less: advance payment recovery (0%) | 0 |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (7,125) |
| 8 | Net before VAT | 135,375 |
| 9 | Add: value added tax (15%) | 20,306 |
| 10 | Net amount payable to the contractor | 155,681 |
Amount in words: One hundred fifty-five thousand six hundred eighty-one Saudi riyals only
Retention held up to this certificate: SAR 19.6K — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 133,000 | 41,550 | 21,700 | 63,250 | 48% |
| Earthworks & foundations | 342,000 | 64,250 | 34,400 | 98,650 | 29% |
| Concrete & structural works | 589,000 | 84,750 | 48,750 | 133,500 | 23% |
| Mechanical, electrical & plumbing | 456,000 | 40,300 | 25,450 | 65,750 | 14% |
| Finishes & external works | 285,000 | 15,850 | 10,600 | 26,450 | 9% |
| Testing & commissioning | 95,000 | 2,300 | 1,600 | 3,900 | 4% |
| Total | 1,900,000 | 249,000 | 142,500 | 391,500 | 21% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Ammar Y. Bakhashab
Supervising engineer
Eng. Ibrahim A. Al-Ghamdi
Project manager
Eng. Omar H. Bawazir
Finance & contracts
Khalid N. Al-Mutairi
Final approver
Dr. Abdullah S. Al-Qahtani