Kingdom of Saudi Arabia
Riyadh Chamber of Commerce & Industry
General Directorate of Finance & Procurement — Contracts & Procurement Department
- Certificate no.
- 3
- Date
- 2025-10-13
- Hijri
- 21 Rabiʻ II 1447 AH
- Reference
- PAY-2025-012-03
Interim payment certificate no. (3)
For the work of September 2025
- Contract number
- RC/2025/012
- Supplier-portal reference
- 2503950550
- Contract
- Network & server equipment — disaster recovery site
- Contractor
- Smart Link Telecom & Security Systems Co.
- Contractor VAT number
- 340303165720003
- Project
- Disaster Recovery Centre for the Chamber’s Systems
- Contract period
- 2025-06-01 — 2026-11-30
- Original contract value
- 1,900,000
- Current contract value
- 1,900,000
- Linked milestone
- Earthworks & foundations complete · MS-G2 Designs approved
Certificate summary (SAR)
| 1 | Total value of work completed to date | 249,000 |
| 2 | Less: previous certificates | (147,000) |
| 3 | Value of work in this certificate | 102,000 |
| 4 | Less: retention (5%) | (5,100) |
| 5 | Less: advance payment recovery (0%) | 0 |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (5,100) |
| 8 | Net before VAT | 96,900 |
| 9 | Add: value added tax (15%) | 14,535 |
| 10 | Net amount payable to the contractor | 111,435 |
Amount in words: One hundred eleven thousand four hundred thirty-five Saudi riyals only
Retention held up to this certificate: SAR 12.5K — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 133,000 | 24,300 | 15,900 | 40,200 | 30% |
| Earthworks & foundations | 342,000 | 37,700 | 25,050 | 62,750 | 18% |
| Concrete & structural works | 589,000 | 50,050 | 34,850 | 84,900 | 14% |
| Mechanical, electrical & plumbing | 456,000 | 24,050 | 17,800 | 41,850 | 9% |
| Finishes & external works | 285,000 | 9,500 | 7,300 | 16,800 | 6% |
| Testing & commissioning | 95,000 | 1,400 | 1,100 | 2,500 | 3% |
| Total | 1,900,000 | 147,000 | 102,000 | 249,000 | 13% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Ammar Y. Bakhashab
Supervising engineer
Eng. Ibrahim A. Al-Ghamdi
Project manager
Eng. Omar H. Bawazir
Finance & contracts
Khalid N. Al-Mutairi
Final approver
Dr. Abdullah S. Al-Qahtani