Riyadh ChamberMunjaz11My actionsNotifications

Certificate ⁦2⁩ — August 2025

Network & server equipment — disaster recovery site

Kingdom of Saudi Arabia

Riyadh Chamber of Commerce & Industry

General Directorate of Finance & Procurement — Contracts & Procurement Department

Certificate no.
2
Date
⁦2025-08-30⁩
Hijri
7 Rabiʻ I 1447 AH
Reference
PAY-2025-012-02

Interim payment certificate no. (⁦2⁩)

For the work of August 2025

Contract number
RC/2025/012
Supplier-portal reference
2503950550
Contract
Network & server equipment — disaster recovery site
Contractor
Smart Link Telecom & Security Systems Co.
Contractor VAT number
340303165720003
Project
Disaster Recovery Centre for the Chamber’s Systems
Contract period
⁦2025-06-01⁩ — ⁦2026-11-30⁩
Original contract value
1,900,000
Current contract value
1,900,000
Linked milestone
Earthworks & foundations complete · MS-G2 Designs approved

Certificate summary (SAR)

1Total value of work completed to date147,000
2Less: previous certificates(55,500)
3Value of work in this certificate91,500
4Less: retention (⁦5%⁩)(4,575)
5Less: advance payment recovery (⁦0%⁩)0
6Less: delay and breach penalties0
7Total deductions(4,575)
8Net before VAT86,925
9Add: value added tax (15%)13,039
10Net amount payable to the contractor99,964

Amount in words: Ninety-nine thousand nine hundred sixty-four Saudi riyals only

Retention held up to this certificate: SAR 7,350 — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation133,0009,25014,50023,750⁦18%⁩
Earthworks & foundations342,00014,30022,75037,050⁦11%⁩
Concrete & structural works589,00018,90031,25050,150⁦9%⁩
Mechanical, electrical & plumbing456,0009,00015,70024,700⁦5%⁩
Finishes & external works285,0003,5506,3509,900⁦3%⁩
Testing & commissioning95,0005009501,450⁦2%⁩
Total1,900,00055,50091,500147,000⁦8%⁩

Amounts in Saudi riyals.

Signatures and approvals

Contractor’s representative

Eng. Ammar Y. Bakhashab

Bakhashab⁦2025-08-30⁩

Supervising engineer

Eng. Ibrahim A. Al-Ghamdi

Al-Ghamdi⁦2025-09-01⁩

Project manager

Eng. Omar H. Bawazir

Bawazir⁦2025-09-04⁩

Finance & contracts

Khalid N. Al-Mutairi

Al-Mutairi⁦2025-09-07⁩

Final approver

Dr. Abdullah S. Al-Qahtani

Al-Qahtani⁦2025-09-10⁩
Issued electronically through Munjaz Integration-ready for the Dynamics 365 supplier portal

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2025-08-30⁩

    Eng. Ammar Y. Bakhashab

  2. Engineer verifies quantities⁦2025-09-01⁩

    Eng. Ibrahim A. Al-Ghamdi · Director, Engineering Supervision of Construction Projects

    Took 2 days

  3. Project manager certifies⁦2025-09-04⁩

    Eng. Omar H. Bawazir · Director, IT Infrastructure

    Took 3 days

  4. Payment order prepared⁦2025-09-07⁩

    Khalid N. Al-Mutairi · Senior Finance & Procurement SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2025-09-10⁩

    Dr. Abdullah S. Al-Qahtani · Secretary-General

    Took 3 days

You are viewing as Dr. Noura M. Al-Otaibi

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneEarthworks & foundations completeDone · ⁦2025-11-01⁩
  2. Project milestoneMS-G2Designs approvedMilestone approved ⁦2026-03-17⁩1 evidence file

Deliverables & completion certificates

No deliverable is tied to this milestone — the evidence is the milestone’s approval and its files.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itKhalid N. Al-Mutairi → Dr. Abdullah S. Al-Qahtani
  • Whoever verified quantities does not prepare the payment orderEng. Ibrahim A. Al-Ghamdi → Khalid N. Al-Mutairi
  • The project manager does not approve the paymentEng. Omar H. Bawazir → Dr. Abdullah S. Al-Qahtani

Certificate history

10 September 2025

  1. Payment: Dr. Abdullah S. Al-Qahtani signed “Final approval”

    2025-09-10 13:00

7 September 2025

  1. Approval: Khalid N. Al-Mutairi signed “Payment order prepared”

    2025-09-07 13:00

4 September 2025

  1. Approval: Eng. Omar H. Bawazir signed “Project manager certifies”

    2025-09-04 13:00

1 September 2025

  1. Approval: Eng. Ibrahim A. Al-Ghamdi signed “Engineer verifies quantities”

    2025-09-01 13:00

30 August 2025

  1. Approval: Contractor signed “Certificate submitted”

    2025-08-30 09:00
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close