Kingdom of Saudi Arabia
Riyadh Chamber of Commerce & Industry
General Directorate of Finance & Procurement — Contracts & Procurement Department
- Certificate no.
- 3
- Date
- 2025-07-06
- Hijri
- 11 Muharram 1447 AH
- Reference
- PAY-2025-019-03
Interim payment certificate no. (3)
For the work of June 2025
- Contract number
- RC/2025/019
- Supplier-portal reference
- 2504440641
- Contract
- Correspondence & document management system — supply & implementation
- Contractor
- Integrated Business Systems Co.
- Contractor VAT number
- 310104366820003
- Project
- Correspondence & Document Management System
- Contract period
- 2025-02-16 — 2026-09-30
- Original contract value
- 580,000
- Current contract value
- 580,000
- Linked milestone
- Design approved · MS-G1 Project plan approved
Certificate summary (SAR)
| 1 | Total value of work completed to date | 83,000 |
| 2 | Less: previous certificates | (49,000) |
| 3 | Value of work in this certificate | 34,000 |
| 4 | Less: retention (10%) | (3,400) |
| 5 | Less: advance payment recovery (10%) | (3,400) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (6,800) |
| 8 | Net before VAT | 27,200 |
| 9 | Add: value added tax (15%) | 4,080 |
| 10 | Net amount payable to the contractor | 31,280 |
Amount in words: Thirty-one thousand two hundred eighty Saudi riyals only
Retention held up to this certificate: SAR 8,300 — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Analysis & design | 87,000 | 11,050 | 7,200 | 18,250 | 21% |
| Licences & platform | 116,000 | 12,900 | 8,700 | 21,600 | 19% |
| Build & configuration | 174,000 | 14,600 | 10,300 | 24,900 | 14% |
| Systems integration | 87,000 | 5,750 | 4,200 | 9,950 | 11% |
| Testing & acceptance | 58,000 | 2,850 | 2,150 | 5,000 | 9% |
| Training & run | 58,000 | 1,850 | 1,450 | 3,300 | 6% |
| Total | 580,000 | 49,000 | 34,000 | 83,000 | 14% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Mona F. Al-Harbi
Supervising engineer
Hussam T. Al-Qurashi
Project manager
Dana S. Al-Saleh
Finance & contracts
Khalid N. Al-Mutairi
Final approver
Munirah A. Al-Khalidi