Interim payment certificate no. (8)
For the work of February 2026
- Contract number
- RC/2025/019
- Supplier-portal reference
- 2504440641
- Contract
- Correspondence & document management system — supply & implementation
- Contractor
- Integrated Business Systems Co.
- Contractor VAT number
- 310104366820003
- Project
- Correspondence & Document Management System
- Contract period
- 2025-02-16 — 2026-09-30
- Original contract value
- 580,000
- Current contract value
- 580,000
- Linked milestone
- Integration & UAT · MS-G3 Build complete
Certificate summary (SAR)
| 1 | Total value of work completed to date | 342,500 |
| 2 | Less: previous certificates | (291,000) |
| 3 | Value of work in this certificate | 51,500 |
| 4 | Less: retention (10%) | (5,150) |
| 5 | Less: advance payment recovery (10%) | (5,150) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (10,300) |
| 8 | Net before VAT | 41,200 |
| 9 | Add: value added tax (15%) | 6,180 |
| 10 | Net amount payable to the contractor | 47,380 |
Amount in words: Forty-seven thousand three hundred eighty Saudi riyals only
Retention held up to this certificate: SAR 34.3K — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Analysis & design | 87,000 | 66,750 | 8,600 | 75,350 | 87% |
| Licences & platform | 116,000 | 77,200 | 11,850 | 89,050 | 77% |
| Build & configuration | 174,000 | 86,200 | 16,550 | 102,750 | 59% |
| Systems integration | 87,000 | 33,700 | 7,400 | 41,100 | 47% |
| Testing & acceptance | 58,000 | 16,450 | 4,100 | 20,550 | 35% |
| Training & run | 58,000 | 10,700 | 3,000 | 13,700 | 24% |
| Total | 580,000 | 291,000 | 51,500 | 342,500 | 59% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Mona F. Al-Harbi
Supervising engineer
Hussam T. Al-Qurashi
Project manager
Dana S. Al-Saleh
Finance & contracts
Khalid N. Al-Mutairi
Final approver
Munirah A. Al-Khalidi