Riyadh ChamberMunjaz11My actionsNotifications

Certificate ⁦10⁩ — May 2026

Correspondence & document management system — supply & implementation

Kingdom of Saudi Arabia

Riyadh Chamber of Commerce & Industry

General Directorate of Finance & Procurement — Contracts & Procurement Department

Certificate no.
10
Date
⁦2026-06-04⁩
Hijri
18 Dhuʻl-Hijjah 1447 AH
Reference
PAY-2025-019-10

Interim payment certificate no. (⁦10⁩)

For the work of May 2026

Contract number
RC/2025/019
Supplier-portal reference
2504440641
Contract
Correspondence & document management system — supply & implementation
Contractor
Integrated Business Systems Co.
Contractor VAT number
310104366820003
Project
Correspondence & Document Management System
Contract period
⁦2025-02-16⁩ — ⁦2026-09-30⁩
Original contract value
580,000
Current contract value
580,000
Linked milestone
Go-live · MS-G4 Testing & acceptance complete

Certificate summary (SAR)

1Total value of work completed to date439,500
2Less: previous certificates(390,500)
3Value of work in this certificate49,000
4Less: retention (⁦10%⁩)(4,900)
5Less: advance payment recovery (⁦10%⁩)(4,900)
6Less: delay and breach penalties0
7Total deductions(9,800)
8Net before VAT39,200
9Add: value added tax (15%)5,880
10Net amount payable to the contractor45,080

Amount in words: Forty-five thousand eighty Saudi riyals only

Retention held up to this certificate: SAR 44K — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Analysis & design87,00081,1005,90087,000⁦100%⁩
Licences & platform116,000105,55010,450116,000⁦100%⁩
Build & configuration174,000122,55017,250139,800⁦80%⁩
Systems integration87,00045,1007,65052,750⁦61%⁩
Testing & acceptance58,00021,9504,40026,350⁦45%⁩
Training & run58,00014,2503,35017,600⁦30%⁩
Total580,000390,50049,000439,500⁦76%⁩

Amounts in Saudi riyals.

Signatures and approvals

Contractor’s representative

Mona F. Al-Harbi

Al-Harbi⁦2026-06-04⁩

Supervising engineer

Hussam T. Al-Qurashi

Al-Qurashi⁦2026-06-06⁩

Project manager

Dana S. Al-Saleh

Al-Saleh⁦2026-06-09⁩

Finance & contracts

Khalid N. Al-Mutairi

Al-Mutairi⁦2026-06-12⁩

Final approver

Munirah A. Al-Khalidi

Al-Khalidi⁦2026-06-15⁩
Issued electronically through Munjaz Integration-ready for the Dynamics 365 supplier portal

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2026-06-04⁩

    Mona F. Al-Harbi

  2. Engineer verifies quantities⁦2026-06-06⁩

    Hussam T. Al-Qurashi · Senior Software Engineer – Integration

    Took 2 days

  3. Project manager certifies⁦2026-06-09⁩

    Dana S. Al-Saleh · Director, Enterprise Systems & Integration

    Took 3 days

  4. Payment order prepared⁦2026-06-12⁩

    Khalid N. Al-Mutairi · Senior Finance & Procurement SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2026-06-15⁩

    Munirah A. Al-Khalidi · Director General, Finance & Procurement

    Took 3 days

You are viewing as Dr. Noura M. Al-Otaibi

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneGo-liveDone · ⁦2026-06-16⁩
  2. Project milestoneMS-G4Testing & acceptance completeMilestone approved ⁦2026-08-28⁩1 evidence file

Deliverables & completion certificates

Every linked deliverable is accepted with a completion certificate.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itKhalid N. Al-Mutairi → Munirah A. Al-Khalidi
  • Whoever verified quantities does not prepare the payment orderHussam T. Al-Qurashi → Khalid N. Al-Mutairi
  • The project manager does not approve the paymentDana S. Al-Saleh → Munirah A. Al-Khalidi

Certificate history

15 June 2026

  1. Payment: Munirah A. Al-Khalidi signed “Final approval”

    2026-06-15 13:00

12 June 2026

  1. Approval: Khalid N. Al-Mutairi signed “Payment order prepared”

    2026-06-12 13:00

9 June 2026

  1. Approval: Dana S. Al-Saleh signed “Project manager certifies”

    2026-06-09 13:00

6 June 2026

  1. Approval: Hussam T. Al-Qurashi signed “Engineer verifies quantities”

    2026-06-06 13:00

4 June 2026

  1. Approval: Contractor signed “Certificate submitted”

    2026-06-04 09:00
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close