RC/2025/019
Terms, guarantees, milestones, variation orders and payment certificates.
From original to current value
The original value and each approved variation
90% of the current value paid
Paid
522Kof a current value of SAR 580K
Value of each certificate
The last 13 — gross and net
Approved: 13
Count: 13 · in the approval chain: 0
| Certificate | Submitted | Gross | Retention | Deductions | VAT | Net | Status | |
|---|---|---|---|---|---|---|---|---|
| Certificate 13October 2026 | 2026-10-25 | 19K | 1,900 | 1,900 | 2,280 | 17.5K | Approved | |
| Certificate 12August 2026 | 2026-09-07 | 29K | 2,900 | 2,900 | 3,480 | 26.7K | Approved | |
| Certificate 11July 2026 | 2026-07-22 | 34.5K | 3,450 | 3,450 | 4,140 | 31.7K | Approved | |
| Certificate 10May 2026 | 2026-06-04 | 49K | 4,900 | 4,900 | 5,880 | 45.1K | Approved | |
| Certificate 9March 2026 | 2026-04-18 | 48K | 4,800 | 4,800 | 5,760 | 44.2K | Approved | |
| Certificate 8February 2026 | 2026-03-01 | 51.5K | 5,150 | 5,150 | 6,180 | 47.4K | Approved | |
| Certificate 7December 2025 | 2026-01-13 | 60.5K | 6,050 | 6,050 | 7,260 | 55.7K | Approved | |
| Certificate 6November 2025 | 2025-11-26 | 48.5K | 4,850 | 4,850 | 5,820 | 44.6K | Approved | |
| Certificate 5September 2025 | 2025-10-09 | 51.5K | 5,150 | 5,150 | 6,180 | 47.4K | Approved | |
| Certificate 4August 2025 | 2025-08-23 | 47.5K | 4,750 | 4,750 | 5,700 | 43.7K | Approved | |
| Certificate 3June 2025 | 2025-07-06 | 34K | 3,400 | 3,400 | 4,080 | 31.3K | Approved | |
| Certificate 2April 2025 | 2025-05-20 | 30K | 3,000 | 3,000 | 3,600 | 27.6K | Approved | |
| Certificate 1March 2025 | 2025-04-02 | 19K | 1,900 | 1,900 | 2,280 | 17.5K | Approved |