Riyadh ChamberMunjaz11My actionsNotifications

Certificate ⁦4⁩ — April 2026

Entrepreneurship centre & co-working spaces — construction

Kingdom of Saudi Arabia

Riyadh Chamber of Commerce & Industry

General Directorate of Finance & Procurement — Contracts & Procurement Department

Certificate no.
4
Date
⁦2026-04-22⁩
Hijri
5 Dhuʻl-Qiʻdah 1447 AH
Reference
PAY-2025-025-04

Interim payment certificate no. (⁦4⁩)

For the work of April 2026

Contract number
RC/2025/025
Supplier-portal reference
2504860719
Contract
Entrepreneurship centre & co-working spaces — construction
Contractor
Al-Bunyan Al-Rasekh Contracting Co.
Contractor VAT number
310102487310003
Project
Entrepreneurship Centre & Co-working Spaces — with the Riyadh Region Municipality
Contract period
⁦2025-08-03⁩ — ⁦2027-08-31⁩
Original contract value
9,800,000
Current contract value
9,800,000
Linked milestone
Structure complete · MS-G3 Build complete

Certificate summary (SAR)

1Total value of work completed to date2,266,000
2Less: previous certificates(1,531,000)
3Value of work in this certificate735,000
4Less: retention (⁦10%⁩)(73,500)
5Less: advance payment recovery (⁦10%⁩)(73,500)
6Less: delay and breach penalties0
7Total deductions(147,000)
8Net before VAT588,000
9Add: value added tax (15%)88,200
10Net amount payable to the contractor676,200

Amount in words: Six hundred seventy-six thousand two hundred Saudi riyals only

Retention held up to this certificate: SAR 226.6K — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation686,000255,050110,900365,950⁦53%⁩
Earthworks & foundations1,764,000394,750176,300571,050⁦32%⁩
Concrete & structural works3,038,000521,200251,500772,700⁦25%⁩
Mechanical, electrical & plumbing2,352,000248,250132,450380,700⁦16%⁩
Finishes & external works1,470,00097,60055,350152,950⁦10%⁩
Testing & commissioning490,00014,1508,50022,650⁦5%⁩
Total9,800,0001,531,000735,0002,266,000⁦23%⁩

Amounts in Saudi riyals.

Signatures and approvals

Contractor’s representative

Eng. Hamad S. Al-Hajri

Al-Hajri⁦2026-04-22⁩

Supervising engineer

Eng. Ibrahim A. Al-Ghamdi

Al-Ghamdi⁦2026-04-24⁩

Project manager

Eng. Ibrahim A. Al-Ghamdi

Al-Ghamdi⁦2026-04-27⁩

Finance & contracts

Khalid N. Al-Mutairi

Al-Mutairi⁦2026-04-30⁩

Final approver

Dr. Abdullah S. Al-Qahtani

Al-Qahtani⁦2026-05-03⁩
Issued electronically through Munjaz Integration-ready for the Dynamics 365 supplier portal

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2026-04-22⁩

    Eng. Hamad S. Al-Hajri

  2. Engineer verifies quantities⁦2026-04-24⁩

    Eng. Ibrahim A. Al-Ghamdi · Director, Engineering Supervision of Construction Projects

    Took 2 days

  3. Project manager certifies⁦2026-04-27⁩

    Eng. Ibrahim A. Al-Ghamdi · Director, Engineering Supervision of Construction Projects

    Took 3 days

  4. Payment order prepared⁦2026-04-30⁩

    Khalid N. Al-Mutairi · Senior Finance & Procurement SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2026-05-03⁩

    Dr. Abdullah S. Al-Qahtani · Secretary-General

    Took 3 days

You are viewing as Dr. Noura M. Al-Otaibi

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneStructure completeLate · ⁦2026-09-24⁩
  2. Project milestoneMS-G3Build completeMilestone not approved yet

Deliverables & completion certificates

Not every completion certificate is issued yet — the amount tied to the milestone is not released before its deliverables are accepted.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itKhalid N. Al-Mutairi → Dr. Abdullah S. Al-Qahtani
  • Whoever verified quantities does not prepare the payment orderEng. Ibrahim A. Al-Ghamdi → Khalid N. Al-Mutairi
  • The project manager does not approve the paymentEng. Ibrahim A. Al-Ghamdi → Dr. Abdullah S. Al-Qahtani

Certificate history

3 May 2026

  1. Payment: Dr. Abdullah S. Al-Qahtani signed “Final approval”

    2026-05-03 13:00

30 April 2026

  1. Approval: Khalid N. Al-Mutairi signed “Payment order prepared”

    2026-04-30 13:00

27 April 2026

  1. Approval: Eng. Ibrahim A. Al-Ghamdi signed “Project manager certifies”

    2026-04-27 13:00

24 April 2026

  1. Approval: Eng. Ibrahim A. Al-Ghamdi signed “Engineer verifies quantities”

    2026-04-24 13:00

22 April 2026

  1. Approval: Contractor signed “Certificate submitted”

    2026-04-22 09:00