Certificate ⁦3⁩ — January 2026

Entrepreneurship centre & co-working spaces — construction

Kingdom of Saudi Arabia

Riyadh Chamber of Commerce & Industry

General Directorate of Finance & Procurement — Contracts & Procurement Department

Certificate no.
3
Date
⁦2026-02-08⁩
Hijri
20 Shaʻban 1447 AH
Reference
PAY-2025-025-03

Interim payment certificate no. (⁦3⁩)

For the work of January 2026

Contract number
RC/2025/025
Supplier-portal reference
2504860719
Contract
Entrepreneurship centre & co-working spaces — construction
Contractor
Al-Bunyan Al-Rasekh Contracting Co.
Contractor VAT number
310102487310003
Project
Entrepreneurship Centre & Co-working Spaces — with the Riyadh Region Municipality
Contract period
⁦2025-08-03⁩ — ⁦2027-08-31⁩
Original contract value
9,800,000
Current contract value
9,800,000
Linked milestone
Earthworks & foundations complete · MS-G2 Designs approved

Certificate summary (SAR)

1Total value of work completed to date1,531,000
2Less: previous certificates(916,000)
3Value of work in this certificate615,000
4Less: retention (⁦10%⁩)(61,500)
5Less: advance payment recovery (⁦10%⁩)(61,500)
6Less: delay and breach penalties0
7Total deductions(123,000)
8Net before VAT492,000
9Add: value added tax (15%)73,800
10Net amount payable to the contractor565,800

Amount in words: Five hundred sixty-five thousand eight hundred Saudi riyals only

Retention held up to this certificate: SAR 153.1K — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation686,000152,10095,200247,300⁦36%⁩
Earthworks & foundations1,764,000235,600150,200385,800⁦22%⁩
Concrete & structural works3,038,000311,900210,150522,050⁦17%⁩
Mechanical, electrical & plumbing2,352,000149,100108,100257,200⁦11%⁩
Finishes & external works1,470,00058,80044,550103,350⁦7%⁩
Testing & commissioning490,0008,5006,80015,300⁦3%⁩
Total9,800,000916,000615,0001,531,000⁦16%⁩

Amounts in Saudi riyals.

Signatures and approvals

Contractor’s representative

Eng. Hamad S. Al-Hajri

Al-Hajri⁦2026-02-08⁩

Supervising engineer

Eng. Ibrahim A. Al-Ghamdi

Al-Ghamdi⁦2026-02-10⁩

Project manager

Eng. Ibrahim A. Al-Ghamdi

Al-Ghamdi⁦2026-02-13⁩

Finance & contracts

Khalid N. Al-Mutairi

Al-Mutairi⁦2026-02-16⁩

Final approver

Dr. Abdullah S. Al-Qahtani

Al-Qahtani⁦2026-02-19⁩
Issued electronically through Munjaz Integration-ready for the Dynamics 365 supplier portal

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2026-02-08⁩

    Eng. Hamad S. Al-Hajri

  2. Engineer verifies quantities⁦2026-02-10⁩

    Eng. Ibrahim A. Al-Ghamdi · Director, Engineering Supervision of Construction Projects

    Took 2 days

  3. Project manager certifies⁦2026-02-13⁩

    Eng. Ibrahim A. Al-Ghamdi · Director, Engineering Supervision of Construction Projects

    Took 3 days

  4. Payment order prepared⁦2026-02-16⁩

    Khalid N. Al-Mutairi · Senior Finance & Procurement SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2026-02-19⁩

    Dr. Abdullah S. Al-Qahtani · Secretary-General

    Took 3 days

You are viewing as Dr. Noura M. Al-Otaibi

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneEarthworks & foundations completeDone · ⁦2026-03-03⁩
  2. Project milestoneMS-G2Designs approvedMilestone approved ⁦2026-08-04⁩1 evidence file

Deliverables & completion certificates

Every linked deliverable is accepted with a completion certificate.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itKhalid N. Al-Mutairi → Dr. Abdullah S. Al-Qahtani
  • Whoever verified quantities does not prepare the payment orderEng. Ibrahim A. Al-Ghamdi → Khalid N. Al-Mutairi
  • The project manager does not approve the paymentEng. Ibrahim A. Al-Ghamdi → Dr. Abdullah S. Al-Qahtani

Certificate history

19 February 2026

  1. Payment: Dr. Abdullah S. Al-Qahtani signed “Final approval”

    2026-02-19 13:00

16 February 2026

  1. Approval: Khalid N. Al-Mutairi signed “Payment order prepared”

    2026-02-16 13:00

13 February 2026

  1. Approval: Eng. Ibrahim A. Al-Ghamdi signed “Project manager certifies”

    2026-02-13 13:00

10 February 2026

  1. Approval: Eng. Ibrahim A. Al-Ghamdi signed “Engineer verifies quantities”

    2026-02-10 13:00

8 February 2026

  1. Approval: Contractor signed “Certificate submitted”

    2026-02-08 09:00
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close